7 novembre 2018 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

DARPA Names Potential Sites for Launch Challenge, Eighteen Teams Prequalify

Teams focus on qualification phase in challenge aimed at launching small payloads on short notice

OUTREACH@DARPA.MIL

11/6/2018

DARPA has narrowed the potential launch locations for the DARPA Launch Challenge to eight, with options for both vertical and horizontal launch. The challenge will culminate in late 2019 with two separate launches to low Earth orbit within weeks of each other from two different sites. Competitors will receive information about the final launch sites, payloads, and targeted orbit in the weeks prior to each launch.

The potential sites are spread across the United States:

  • California Spaceport, Vandenberg Air Force Base
  • Cape Canaveral Spaceport, Florida
  • Cecil Spaceport, Jacksonville, Florida
  • Mid-Atlantic Regional Spaceport, Wallops Island, Virginia
  • Mojave Air and Space Port, California
  • Naval Outlying Field, San Nicolas Island, California
  • Pacific Spaceport Complex Alaska, Kodiak
  • Spaceport America, Truth or Consequences, New Mexico

Eighteen teams have prequalified to participate in the challenge, passing the first hurdle in the milestone process by proposing a viable solution for flexible and responsive launch. The diverse pool of applicants reflects the growth of the small commercial launch industry, and its potential to support emerging national security needs.

“Response from teams with different ways of achieving flexible and responsive launch solutions on short notice has been tremendous,” said Todd Master, program manager for the Launch Challenge in DARPA's Tactical Technology Office. “The different approaches to technologies used, launch requirements, fuel use, and teaming are a testament to the evolving space community.”

To successfully pass the qualification phase, potential competitors must complete three discrete applications. Potential competitors submitted pre-qualification applications in mid-October, and the DARPA Launch Challenge application is due by Nov. 30. Teams also must submit and receive acceptance of an FAA license application by Feb. 1, 2019.

The complexity of commercial space transportation regulations can present challenges for both new and experienced applicants. Teams are encouraged to consult with the FAA well in advance of submitting a launch license application to reduce programmatic risk by identifying and addressing potential regulatory questions or issues.

If teams successfully complete all three steps, they will qualify for the launch phase and receive an initial $400,000 cash prize. Teams successfully completing the first launch will receive a $2 million prize. For a successful second launch, prizes of $10 million, $9 million and $8 million are available for the top three teams respectively, ranked by factors including mass, time to orbit, and orbit accuracy.

https://www.darpa.mil/news-events/2018-11-06

Sur le même sujet

  • Delays Cause Two-Year, $1.5B Extension For F-35 Block 4

    13 mai 2020 | International, Aérospatial

    Delays Cause Two-Year, $1.5B Extension For F-35 Block 4

    Steve Trimble The U.S. Government Accountability Office (GAO) said on May 12 that the Lockheed Martin F-35 Block 4 program must be extended two years due to development delays, adding $1.5 billion to the overall price tag. The original schedule called for completing the Block 4 modernization program in 2024, but the timeline must be extended to 2026, GAO said in the watchdog agency's annual review of the F-35 program. The F-35 Joint Program Office initially estimated the cost to develop all 66 new capabilities in Block 4 would be $10.6 billion. The two-year extension to deliver Block 4 raises the development cost to $12.1 billion, with another $3.4 billion budgeted to procure and insert the capabilities in future U.S. F-35s, GAO said. The Block 4 delays started in 2019. Lockheed planned to deliver the first eight Block 4 capabilities last year, but only one—the automatic ground collision avoidance system—entered service, GAO said. In another example, Lockheed delivered software last year to enable the interim full-motion video capability for the Marine Corps F-35Bs, but failed to deliver the associated hardware, the report said. As Block 4 capabilities have entered testing, the Defense Department's operational testers have noticed other problems. Some of the new capabilities have “caused issues” with existing F-35 functions that previously worked, GAO said. “The contractor had not performed adequate testing of the software before delivering it to the test fleet,” GAO said. For its part, the contractor acknowledged the issues and said they would conduct additional testing in software laboratories before releasing future software blocks, GAO added. https://aviationweek.com/aerospace/aircraft-propulsion/delays-cause-two-year-15b-extension-f-35-block-4

  • Thales reinforces Air Surveillance capabilities for Sweden with SMART-L Multi Mission Long-Range radars

    6 juillet 2023 | International, C4ISR

    Thales reinforces Air Surveillance capabilities for Sweden with SMART-L Multi Mission Long-Range radars

    The SMART L MM/F will contribute to maintaining Swedish airspace sovereignty and will provide superior situational awareness at all times.

  • Ask The Expert: The Digital Engineering Imperative For Aerospace & Defense

    1 février 2022 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

    Ask The Expert: The Digital Engineering Imperative For Aerospace & Defense

Toutes les nouvelles