25 juin 2019 | Local, Naval

Cost of 15 new Canadian warships rises to $70 billion: PBO report

By Christian Paas-Lang

Canada's 15 new warships will cost almost $70 billion over the next quarter-century, according to Parliament's budget watchdog, and the cost could change further depending on the final design of the ships and when they actually get built.

The estimate, released in a report by the parliamentary budget office Friday, is up substantially from a Canadian government estimate in 2017 that pegged the price of the project at between $56 billion and $60 billion. The 2017 estimate was itself a revision of the project's original $26-billion price tag.

Also in 2017, the PBO estimated the total cost of the ships to be $61.8 billion, but its report released Friday updates that to reflect the design of the ships — frigates known as “Type 26” — which wasn't known at the time. It also accounts for delays in the project.

The Canadian government will now pay out $69.8 billion over 26 years, the PBO estimates.

In a statement released shortly after the PBO report, the Department of National Defence said it remained “confident” in its 2017 estimate, and that the “vast majority” of the difference between the estimates came from the PBO's choice to include taxes in its projections.

Taking away taxes brings the two estimates to within 10 per cent of each other, the DND said.

But the department conceded that any small difference means hundreds of millions of dollars in costs for taxpayers.

The PBO report says the difference in the estimates is due to a later start date for construction and a heavier ship design.

The report assumes ships will start being built by the 2023-2024 fiscal year, three years later than its 2017 projection. As the timeline extends into the future, costs increase due to inflation.

The PBO originally projected a displacement, or weight, of 5,400 tonnes for each ship but the Type 26 design is a heftier 6,790 tonnes per ship, an increase of more than 25 per cent.

The report also includes an analysis of what effect further significant delays would have on the project. For a one-year delay, the PBO estimates, an extra $2.2 billion will be added to the project cost, and a two-year delay would cost the government $4.5 billion.

In an interview Friday, the top bureaucrat in charge of procurement at the DND expressed skepticism that the heavier ships will result in as much increased cost as the PBO suggests, but he did say the potential for delays was something he is “watching more carefully.”

“The labour piece is always where uncertainty can remain,” said Pat Finn, the department's associate deputy minister for material, noting labour can make up around 40 per cent of the cost of a ship.

Finn said the DND is in the “same place” as the PBO on the cost of “slippage” — delays in the project — but that he is confident the structure of the National Shipbuilding Strategy will mean the project could benefit from a skilled workforce and ongoing expertise.

The purchase of additional Arctic patrol ships, announced last month, means there will not be a lapse in efficiency at Irving's Halifax shipyard, which is building the warships, Finn said.

He set a goal for start of construction earlier than the PBO assumes in its report.

“We would say between mid-2022 and mid-2023, we're in-contract and cutting steel,” Finn said.

Potential delays would certainly increase costs, and it would be “absolutely no shock if there was additional delays,” said Dave Perry, a procurement expert with the Canadian Global Affairs Institute.

“To this point in time, the government has not been able to meet any of the timelines that have been put forward publicly,” he added.

Still, the closer you get to construction, Perry said, the less uncertainty there should be about costs and the potential for further delay.

The last thing that might change the final cost of the ships is the specifics of what components are chosen to fill out the design — which radar equipment, for example, Perry said.

The DND is deciding on those components as it reconciles the requirements of the ships with costs.

“You could potentially get a few-percentage-point swing” in price in either direction based on those choices, said Perry.

“But if you're talking about several tens of billions of dollars, a few-percentage-points swing is real money.”

https://globalnews.ca/news/5418997/canada-warships-cost/

Sur le même sujet

  • QinetiQ Target Systems to supply over 40 Hammerhead targets to Canadian Navy

    15 septembre 2017 | Local, Naval

    QinetiQ Target Systems to supply over 40 Hammerhead targets to Canadian Navy

    QinetiQ Target Systems has received a new order from the Royal Canadian Navy (RCN) to deliver more than 40 units of Hammerhead unmanned surface vehicle (USV) targets and several payloads. The latest C$4.7m ($3.86m) order is part of an existing C$35m ($28.75m) framework contract with the Canadian Department of National Defence. http://www.naval-technology.com/news/newsqinetiq-target-systems-to-supply-over-40-hammerhead-targets-to-canadian-navy-5925606

  • Defence Watch: New dates set for budget watchdog's reports on major naval projects

    29 octobre 2020 | Local, Naval

    Defence Watch: New dates set for budget watchdog's reports on major naval projects

    David Pugliese Two reports by the parliamentary budget officer looking into the costs of major Canadian naval equipment projects have been delayed. The Commons Standing Committee on Government Operations and Estimates had unanimously passed a motion in June to request the Office of the Parliamentary Budget Officer undertake a costing analysis of the Royal Canadian Navy's new joint support ships as well as the leasing of the Asterix supply ship from a private firm. The PBO study was to also look at the cost of building the joint support ships in Canada at Seaspan shipyard in Vancouver. The committee asked that the PBO report be provided by Oct. 15. Another motion from the committee, passed later in June, asked the PBO to examine the $60 billion price tag of Canada's proposed new fleet of warships – the Canadian Surface Combatant or CSC. Parliamentary Budget Officer Yves Giroux was tasked to investigate the cost of the CSC as well as examine the cost of two other types of warships: the FREMM and the Type 31. That study was supposed to be presented to the committee by Oct. 22. But those original motions from the committee expired when Parliament was prorogued. So new motions have to be provided to the PBO. The Commons committee passed a new motion on Oct. 19 on the Asterix and Joint Support Ship analysis. That analysis is to be delivered by Nov. 30, PBO spokeswoman Sloane Mask told this newspaper. A date for the analysis to be made public has not yet been determined. “Currently, we are also in the process of confirming the revised timelines for the CSC report,” she added.There is particular interest in the defence community about what the PBO determines is the current price-tag of the Canadian Surface Combatant project. Last year the Liberal government signed an initial deal on CSC that is expected to lead to the eventual construction of 15 warships in the largest single government purchase in Canadian history. Lockheed Martin offered Canada the Type 26 warship designed by BAE in the United Kingdom. Irving is the prime contractor and the vessels will be built at its east coast shipyard. Construction of the first ship isn't expected to begin until the early 2020s. But the Canadian Surface Combatant program has already faced rising costs. In 2008, the then-Conservative government estimated the project would cost roughly $26 billion. But in 2015, Vice-Admiral Mark Norman, then commander of the navy, voiced concern that taxpayers may not have been given all the information about the program, publicly predicting the cost for the warships alone would approach $30 billion. The overall project is currently estimated to cost around $60 billion. “Approximately one-half of the CSC build cost is comprised of labour in the (Irving) Halifax yard and materials,” according to federal government documents obtained by this newspaper through the Access to Information law. But some members of parliament and industry representatives have privately questioned whether the CSC price-tag is too high. There have been suggestions that Canada could dump the Type 26 design and go for a cheaper alternative since the CSC project is still in early stages and costs to withdraw could be covered by savings from a less expensive ship. Canada had already been pitched on alternatives. In December 2017, the French and Italian governments proposed a plan in which Canada could build the FREMM frigate at Irving. Those governments offered to guarantee the cost of the 15 ships at a fixed $30 billion, but that was rejected by the Canadian government. The other type of warship the PBO will look at is the Type 31, which is to be built for the Royal Navy in the United Kingdom. Those ships are to cost less than $500 million each. In 2017, then Parliamentary Budget Officer Jean-Denis Fréchette estimated the CSC program would cost $61.82 billion. The entry of the BAE Type 26 warship in the Canadian competition was controversial from the start and sparked complaints that the procurement process was skewed to favour that vessel. Previously the Liberal government had said only mature existing designs or designs of ships already in service with other navies would be accepted on the grounds they could be built faster and would be less risky. Unproven designs can face challenges if problems are found once the vessel is in the water and operating. But the criteria was changed and the government and Irving accepted the BAE design, though at the time it existed only on the drawing board. Construction began on the first Type 26 frigate in the summer of 2017 for Britain's Royal Navy. https://www.thechronicleherald.ca/news/canada/defence-watch-new-dates-set-for-budget-watchdogs-reports-on-major-naval-projects-512897/

  • Minister Blair announces defence investments in Halifax at 15th Halifax International Security Forum

    19 novembre 2023 | Local, Aérospatial, Terrestre, Sécurité

    Minister Blair announces defence investments in Halifax at 15th Halifax International Security Forum

    Today, the Honourable Bill Blair, Minister of National Defence, officially opened the 15th annual Halifax International Security Forum.

Toutes les nouvelles