30 janvier 2018 | Local, Aérospatial

Auditor general to issue new fighter jet report in the fall

Lee Berthiaume, The Canadian Press
Published Monday, January 29, 2018 2:03PM EST
Last Updated Monday, January 29, 2018 4:31PM EST

OTTAWA -- Six years after his explosive report on the F-35 derailed the Harper government's plan to buy the controversial stealth aircraft, federal auditor general Michael Ferguson is diving back into the fighter-jet file.

Ferguson's staff have been going over internal government records for several months, though the auditor general's office won't reveal exactly what aspects of the program are under the microscope.

The final report is scheduled for release in the fall.

Ferguson's last report on fighter jets in April 2012 was a bombshell which found senior defence officials twisted rules, downplayed problems and withheld information about the Harper government's plan to buy 65 F-35s.

The report forced the government to suspend the project pending a complete review, which eventually pegged the full cost of buying and operating the F-35s at more than $45 billion.

Six years later, Canada still has not chosen a new fighter jet to replace its aging CF-18s.

It is unlikely the auditor general will find the kind of serious problems with the government's efforts to buy fighter jets as the last time, as the overall procurement system has been revamped with a variety of checks and balances.

The new review could instead turn on the government's plan to buy interim fighter jets and its arguably slow progress in holding a competition to replace the CF-18s, said defence analyst David Perry of the Canadian Global Affairs Institute.

"How much benefit and at what cost will Canada obtain fighter aircraft by virtue of going through an interim fighter purchase as well as doing a life extension?" Perry said.

"For me, one of the biggest concerns is that the process from this point forward is not exactly lightning quick."

The Liberals announced in November that they plan to buy used fighter jets from Australia -- rather than new Super Hornets from Boeing -- as a stop-gap until the entire CF-18 fleet can be replaced.

The new planes were originally expected by 2025, but documents provided to industry last week show the new target is 2031, as the government plans to take its time with a competition.

The delay is almost certain to mean another round of expensive and complicated life extensions to the CF-18s, which will be 50 years old by the time the last are retired.

Previous reports have determined that any life extensions to the CF-18s beyond 2025 would be "a high-risk option in terms of cost, schedule and technical factors."

Many defence analysts and retired military officials have questioned the need for interim fighters and urged an immediate competition, rather than waiting several years.

https://www.ctvnews.ca/politics/auditor-general-to-issue-new-fighter-jet-report-in-the-fall-1.3780244

Sur le même sujet

  • Canada Undefended: Our military readiness is dangerously insufficient. Here’s how to fix it

    18 février 2024 | Local, Sécurité

    Canada Undefended: Our military readiness is dangerously insufficient. Here’s how to fix it

    The recent Defence Department results report provides a clear picture of the overall readiness of the CAF at barely 50 to 60 per cent.

  • Minister Wilkinson to lead ceremonial keel laying for future Joint Support Ship 2

    25 octobre 2023 | Local, Sécurité

    Minister Wilkinson to lead ceremonial keel laying for future Joint Support Ship 2

    Media are invited to attend as Jonathan Wilkinson, Minister of Energy and Natural Resources and MP for North Vancouver, leads a keel laying ceremony at Seaspan Vancouver Shipyards, marking an important milestone in the construction of the second new Joint Support Ship for the Royal Canadian Navy.

  • Government expects to award contract for new fighter jet fleet in 2022 (but admits it could face delays)

    26 avril 2019 | Local, Aérospatial

    Government expects to award contract for new fighter jet fleet in 2022 (but admits it could face delays)

    DAVID PUGLIESE, OTTAWA CITIZEN Though the federal government expects to award a contract for a new fleet of fighter jets in 2022, it admits that schedule is aggressive and could yet face further delays. A request for bids to provide 88 new jets to the Royal Canadian Air Force will be released next month, according to a new update on major Department of National Defence projects released Wednesday, with the proposals to be evaluated by 2021 and a contract to be awarded a year later. But in the update DND also admits that timeline is tenuous. “The approved schedule is considered very aggressive,” it said. “The project team is managing a number of risks which have the potential to impact schedule.” The document doesn't outline the specific risks but DND officials have acknowledged that government negotiations with private contractors on the industrial benefits that are to be linked to the project could cause delays. The Liberals have committed to purchasing the new jets in a program expected to cost up to $19 billion. The competition was launched on Dec. 12, 2017, and Canada expects to examine four different fighter jets as candidates for the RCAF's new fleet. The project team is managing a number of risks which have the potential to impact schedule The first of the jets is expected to be delivered in the mid-2020s, with the full capability available in the early 2030s, according to the DND document. The document also outlines the plan to purchase used Australian F-18s in the interim, which the RACF will use to boost the capability of its current fleet of CF-18s until the new generation aircraft are in service. The first of the Australian jets has already been delivered, with final delivery set for the end of 2021, according to the update. However, the parliamentary budget officer has found this interim solution could cost more than $1 billion, and the auditor general's office has pointed out that the air force is lacking pilots and maintenance crews for the planes it already operates. Wednesday's DND update points out success stories as well as challenges with some of DND's multi-billion dollar projects. Some programs, such as the purchase of Chinook helicopters and tactical armoured patrol vehicles, are completed or are nearing completion with few problems. A new $2-billion program to buy heavy trucks is among those expected to be proceed without issues. Canada also expects to award a contact next year for a mid-life upgrade of the fleet of Cormorant search-and-rescue helicopters, and the conversion of former U.S. presidential helicopters so they can join the flight line for rescue operations. But the report warns there could be problems with other upcoming projects such as the purchase of a fleet of drones. It noted that there might not be enough procurement staff with the required expertise to move that program forward on schedule. The department hopes to deal with the problem by hiring contractors. A draft invitation to qualify for that project was released April 5 and a contact is expected to be awarded in 2022, the document said. The first of a fleet of new fixed-wing search-and-rescue aircraft, meanwhile, are to be delivered in December. The first plane will be sent to 19 Wing Comox, B.C. in the spring of 2020. The 16 new planes will be phased in between 2020 and 2022. But DND acknowledged it is keeping an eye on the potential that schedule could be affected because of the “complexities associated with transitioning to the new fleet while maintaining the current search and rescue posture.” In addition, DND is keeping watch on problems with its new upgraded light armoured vehicles. Though the vehicles have been delivered on time, some technical issues will be fixed through a retrofit program. There have also been problems with software design and qualification of components in another new fleet of armoured vehicles that will be used for battlefield surveillance, the first of which is to be delivered next year. The first new supply ship for the Royal Canadian Navy, being built in Vancouver, is expected in 2023 but won't be ready for operations until a year later. The delivery of the second supply ship “is currently under review,” the update added. In the meantime, the navy has access to MV Asterix, the supply ship at the heart of the court case involving Vice-Admiral Mark Norman. That ship, currently being leased to the navy by Quebec firm Davie Shipbuilding, was delivered on time and on budget and is considered a procurement success story. https://ottawacitizen.com/news/canada/government-expects-to-award-contract-for-new-fighter-jet-fleet-in-2022-but-admits-it-could-face-delays/wcm/a34c8b83-3838-4ff9-87ac-1741fd434059

Toutes les nouvelles