July 6, 2020 | International, Aerospace

US Air Force delays timeline for testing a laser on a fighter jet

By:

WASHINGTON — The U.S. Air Force's long-planned test of an airborne laser weapon aboard a fighter jet has been delayed until 2023 due to technical challenges and complications spurred by the ongoing coronavirus pandemic, its program head said.

The Air Force's Self-Protect High Energy Laser Demonstrator program, or SHiELD, had originally planned to conduct its first flight demonstration in 2021, but the test has been pushed two years back, said Jeff Heggemeier, SHiELD program manager for the Air Force Research Laboratory.

“This is a really complex technology to try to integrate into that flight environment, and that's ultimately what we're trying to do with this program, is demonstrate that laser technology is mature enough to be able to integrate onto that airborne platform,” he told Defense News in a June 10 interview. “But even things like COVID, and COVID shutting down the economy. That has impacts.”

Beyond that, the future of using laser weapons aboard fighter aircraft is even more unclear. The goal of SHiELD was to give combat jets a way to counter missiles shot by an enemy aircraft or by air defense systems on the ground. But in May, Mike Griffin, the Pentagon's undersecretary of defense for research and engineering, noted that he was “extremely skeptical” that an airborne laser could be used for missile defense.

Asked what that meant for SHiELD, Air Force acquisition czar Will Roper acknowledged that the service is rethinking how it could best use directed-energy technologies. Perhaps the most optimal use for SHiELD wasn't onboard a fighter, he said.

“What I've told that team is, let's have a dialogue,” Roper said during a June 9 event hosted by the Mitchell Institute for Aerospace Studies. “Let's understand the different power levels and what they should correspond to, and let's not make the highest power level that we can dream up and the mission that's the sexiest be the thing that drives us.”

“What I expect to get laser weapons to the goal line has been the humble, but important and very worrisome small drone threat. They continue to show up, they're difficult to attribute — we don't know who is sending them to our installations and tests and things of that nature, and we can't afford to shoot missiles at them,” he added. “So this is a perfect threat to make laser weapons real, and once they're real, we'll do what the military does. We'll look to scale the power.”

Heggemeier said there are many ways the Air Force could spin off laser technologies developed by the SHiELD program, but it's critical the service continue with development so it can gauge the maturity and usefulness of the capabilities.

“I think it's important for us to first remember what the whole point of SHiELD is. The whole point of SHiELD is not an acquisition program where we're turning out hundreds or tens of these laser systems for operational use. What we're trying to do with SHiELD is exactly answer those questions of: ‘Is laser technology mature enough to go on an airborne platform? Have we solved enough of those technical challenges that this is now a feasible thing?' Because there is that concern.”

He also drew a distinction between the tactical, self-defense capability a SHiELD laser would give combat aircraft versus a more powerful laser capable of intercepting highly-advanced ballistic missiles, as the Missile Defense Agency has proposed.

“You're not talking about these really, really long ranges. You're talking about a shorter range and different targets just to protect yourself or your wingman,” Heggemeier said. “Missile defense can mean a lot of things. Some of those missile defense missions are very, very hard, and some of them aren't quite so hard.”

For now, at least, the Air Force's investment in directed energy remains stable. The service's budget lays out cash for high-energy lasers in multiple funding lines. For fiscal 2021, it requested $15.1 million for basic research and $45.1 million for applied research for high-energy laser technology, as well as another $13 million for high-power, solid-state laser technology. In FY20, the service received $14.8 million for basic research and $48.2 million for applied research for laser technologies.

SHiELD is comprised of three elements: the laser itself, which is being developed by Lockheed Martin; the beam control system made by Northrop Grumman; and the pod that encases the weapons system, from Boeing. Heggemeier said the pod is under construction, with integration of the laser and beam control system planned to start next year.

“A lot of the challenge is trying to get all of this stuff into this small pod. If you look at other lasers that are fairly mature, we have other laser systems that some other contractors have built that are ready to be deployed. But these are ground-based systems, and they are much, much more mature,” he said.

In April 2019, the Air Force Research Lab conducted a ground test with a surrogate laser system — the Demonstrator Laser Weapon System, or DLWS, now in use by the Army. The demonstration involved the successful downing of several air-to-air missiles.

“It turns out the DLWS system, when you take everything into account, is a really good surrogate for the laser power on SHiELD,” Heggemeier said.

Because both SHiELD and DLWS generate similar amounts of energy on target — in SHiELD's case, Heggemeier would only say that it amounts to “tens of kilowatts” — the surrogate test gave the lab a good idea how the laser physically affects a target.

In 2019, the team conducted a flight test of a pod with the same outer mold line as the one under development by Boeing. The pod was mounted to an aircraft — Heggemeier declined to specify the model — and flown around Eglin Air Force Base, Florida, to help measure how vibrations, the force of gravity and other environmental factors might influence the performance of the weapon.

Air Force Magazine reported in 2019 that aerial demonstrations of SHiELD would occur onboard an F-15 fighter jet.

https://www.defensenews.com/air/2020/06/30/us-air-force-delays-timeline-for-testing-a-laser-on-a-fighter-jet/

On the same subject

  • Contract Awards by US Department of Defense - October 11, 2019

    October 15, 2019 | International, Aerospace, Naval, Land, C4ISR, Security

    Contract Awards by US Department of Defense - October 11, 2019

    NAVY Electric Boat Corp., Groton, Connecticut, is awarded a $434,370,635 contract for lead yard support and development studies and design efforts related to Virginia class submarines. Work will be performed in Groton, Connecticut (94.1%); Newport News, Virginia (4.8%); and Newport and Quonset, Rhode Island (combined 1.1%), and is expected to be complete by September 2020. The contract provides lead yard support for Virginia class submarines that will maintain, update and support the Virginia class design and related drawings and data for each Virginia class submarine, including technology insertion, throughout its construction and post-shakedown availability period. The contractor will also provide all engineering and related lead yard support necessary for direct maintenance and support of Virginia class ship specifications. In addition, the contract provides development studies and design efforts related to the Virginia class submarine design and design improvements; preliminary and detail component and system design; integration of system engineering, design engineering, test engineering, logistics engineering and production engineering. The contractor will continue development studies and design efforts related to components and systems to accomplish research and development tasks, and prototypes and engineering development models required to fully evaluate new technologies to be inserted in succeeding Virginia class submarines. Fiscal 2014, 2016, 2017, 2018 and 2019 shipbuilding and conversion (SCN) (Navy); and fiscal 2019 research, development, test and engineering (RDT&E) (Navy) funding in the amount of $68,321,021 will be obligated at time of award. Fiscal 2014 shipbuilding and conversion (Navy) funds in the amount of $4,050,000; and fiscal 2019 research, development, test and engineering (Navy) funds in the amount of $7,341,250 will expire at the end of the current fiscal year — fiscal 2018 SCN (38.8%); fiscal 2017 SCN (34.9%); fiscal 2019 RDT&E (10.7%); fiscal 2014 SCN (7.1%); fiscal 2019 SCN (5%); fiscal 2016 SCN (3.4%). This contract was not competitively procured in accordance with Federal Acquisition Regulation 6.302-1(a)(2)(iii) — only one responsible source and no other supplies or services will satisfy agency requirements. The Naval Sea Systems Command, Washington, District of Columbia, is the contracting activity (N00024-20-C-2120). Space Ground Systems Solutions LLC, West Melbourne, Florida, awarded a $17,082,880 cost-plus-fixed-fee contract modification to overall ceiling for previously awarded contract (N00173-15-D-2015) for spacecraft engineering, software, research and development services to the Naval Center for Space Technology (NCST). Specifically, the indefinite-delivery/indefinite-quantity (IDIQ) provides support for software engineering development, maintenance, enhancement and configuration management support for all components contained within the Neptune™ software suite under the direction of the NRL Configuration Control Board, and the VMOC™ software framework under the direction of the VMOC™ program management and software engineering teams. Funding will be obligated for each task order and no funds are obligated on the base IDIQ contract. Work will be performed in Washington, District of Columbia (50%); and West Melbourne, Florida (50%), and is expected to be completed by March 2020. The U.S. Naval Research Laboratory, Washington, District of Columbia, is the contracting activity. Rolls-Royce Corp., Indianapolis, Indiana, is awarded a $9,066,270 modification (P00013) to a previously awarded firm-fixed-price contract (N00019-17-C-0081). This modification exercises an option to procure three spare AE1107C engines in support of the V-22 Osprey program for the government of Japan. Work will be performed in Indianapolis, Indiana, and is expected to be completed in November 2020. Foreign military sales funds in the amount of $9,066,270 will be obligated at time of award, none of which will expire at the end of the current fiscal year. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity. ARMY Northrop Grumman Systems Corp., Huntsville, Alabama, was awarded a $60,619,031 modification (P00185) to contract W31P4Q-08-C-0418 for engineering, logistics, integration, test and evaluation, and program management activities. Work will be performed in Huntsville, Alabama, with an estimated completion date of March 31, 2021. Fiscal 2020 research, development, test and evaluation funds in the amount of $5,000,000 were obligated at the time of the award. U.S. Army Contracting Command, Redstone Arsenal, Alabama, is the contracting activity. BAE Systems Ordnance Systems Inc., Radford, Virginia, was awarded an $8,309,050 cost-plus-fixed-fee contract to incorporate a requirement to stabilize the legacy nitroglycerin area facility at Radford Army Ammunition Plant. One bid was solicited with one bid received. Work will be performed in Radford, Virginia, with an estimated completion date of Dec. 31, 2021. Fiscal 2019 procurement of ammunition, Army funds in the amount of $8,309,050 were obligated at the time of the award. U.S. Army Contracting Command, Rock Island Arsenal, Illinois, is the contracting activity (W52P1J-20-F-0021). DEFENSE LOGISTICS AGENCY Northrop Grumman Systems Corp., El Segundo, California, has been awarded a maximum $24,299,972 firm-fixed-priced delivery order (SPRPA1-19-F-LT31) against a five-year basic ordering agreement (SPRPA1-15-G-001Z) for rudders in support of the F/A-18 aircraft platform. This was a sole-source acquisition using justification 10 U.S. Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is a seven-year contract with no option periods. Location of performance is California, with an Aug. 31, 2026, performance completion date. Using military service is Navy. Type of appropriation is fiscal 2020 through 2026 Navy working capital funds. The contracting activity is the Defense Logistics Agency Aviation, Philadelphia, Pennsylvania. Belleville Shoe Co.,* Belleville, Illinois, has been awarded a maximum $12,524,036 firm-fixed-price, indefinite-delivery/indefinite-quantity contract for Air Force temperate weather, Coyote boots. This was a competitive acquisition with two responses received. This is a one-year base contract with three one-year option periods. Location of performance is Illinois, with an Oct. 10, 2020, performance completion date. Using customer is Air Force. Type of appropriation is fiscal 2019 through 2020 defense working capital funds. The contracting agency is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE1C1-20-D-1208). *Small Business https://www.defense.gov/Newsroom/Contracts/Contract/Article/1988088/source/GovDelivery/

  • Bowen inaugure son centre de R&D aux Ulis

    October 13, 2020 | International, C4ISR, Security

    Bowen inaugure son centre de R&D aux Ulis

    PATRICK DÉSAVIE Le spécialiste des équipements complexes de radiofréquences et de télécommunications Bowen a inauguré le 8 octobre son nouveau centre de R&D aux Ulis (Essonne) où travaillent une cinquantaine de salariés. Spécialisé dans la conception et la fabrication d'équipements complexes de radiofréquence et de télécommunications, le groupe Bowen a inauguré, le 8 octobre son nouveau centre de R&D situé dans la grande zone d'activités de Courtabœuf aux Ulis (Essonne). Spécialisé dans la conception et la fabrication d'équipements complexes de radiofréquence et de télécommunications, le groupe Bowen a inauguré, le 8 octobre son nouveau centre de R&D situé https://www.usinenouvelle.com/article/bowen-inaugure-son-centre-de-r-d-aux-ulis.N1014414 .

  • La NASA et le Pentagone unissent leurs forces

    February 3, 2021 | International, Aerospace

    La NASA et le Pentagone unissent leurs forces

    Les responsables du gouvernement américain et de l'industrie aérospatiale sont en train de faire tomber les barrières vieilles de plusieurs décennies entre les projets spatiaux civils et militaires, en réponse à l'intensification des menaces étrangères au-dessus de l'atmosphère. Le Pentagone et la NASA unissent leurs forces pour se lancer dans des projets tels que l'exploration de la périphérie de la Lune et la prolongation de la durée de vie des satellites. Ce rapprochement est motivé par les activités menées par Moscou et Pékin visant à mettre à mal les intérêts américains dans l'espace, via leurs armes antisatellites, leurs dispositifs de brouillage et d'autres technologies potentiellement hostiles. Le général John Raymond, chef d'état-major de la Space Force (Force spatiale américaine), a récemment dévoilé un partenariat de recherche avec la NASA visant à protéger les satellites des lasers et des cyberattaques. A terme, selon des responsables gouvernementaux et des dirigeants du secteur, la coopération entre civils et militaires devrait s'étendre à la défense des bases que la NASA a prévu d'installer sur le sol lunaire, ainsi qu'à la protection des opérations commerciales américaines censées y extraire de l'eau ou des minerais. L'Opinion du 2 février 2021 - The Wall Street Journal du 1er février 2021

All news