August 7, 2023 | International, Land, Security
US Army greenlights armored vehicle for full-rate production
The Army is now entering full-rate production of its new Armored Multi-Purpose Vehicle following some delays.
April 1, 2020 | International, Aerospace
By: Valerie Insinna
WASHINGTON — The Air Force on Monday logged another critical technical flaw for the KC-46 tanker, this time revolving around excessive fuel leaks.
Under its contract with the service, KC-46 manufacturer Boeing is responsible for paying for a fix to the problem, Air Force spokeswoman Capt. Cara Bousie said in a statement.
“The Air Force and Boeing are working together to determine the root cause and implement corrective actions,” she said. “The KC-46 program office continues to monitor the entire KC-46 fleet and is enhancing acceptance testing of the fuel system to identify potential leaks at the factory where they can be repaired prior to delivery.”
The problem was first discovered in July 2019, but the Air Force did not say why the issue had been escalated to Category 1 status — the designation given to problems with a significant impact on operations or safety. The service also did not immediately comment on questions about what sort of receiver aircraft were most involved with the deficiency or the severity of the problem.
A Boeing spokesman said that the Air Force had discovered 16 aircraft in need of repair, and that seven have already been fixed.
“The KC-46 fuel system is equipped with redundant protection for fuel containment. In some cases with this issue, aircraft maintenance crews are finding fuel between the primary and secondary fuel protection barriers within the system,” the company said in a statement.
Boeing is working with “utmost urgency” to address the problem and implement a fix to the remaining aircraft, the statement said. A Boeing spokesman added it would take about 10 days to retrofit each aircraft at the rapid response depot facility in San Antonio, Texas. The fix was also being incorporated into production line in Everett, Wash., which is currently undergoing a temporary suspension due to COVID-19.
The latest Category 1 deficiency brings the total up to four:
Boeing's fixed-priced firm contract for the development of the KC-46 has a $4.9 billion ceiling that leaves the company responsible for any expenses billed in excess of that amount. So far, the company has paid more than $3.5 billion of its own money to fund corrections to ongoing technical issues.
August 7, 2023 | International, Land, Security
The Army is now entering full-rate production of its new Armored Multi-Purpose Vehicle following some delays.
June 28, 2021 | International, Aerospace
The Air Force's biggest program is making steady progress in meeting its sustainment objectives.
October 15, 2024 | International, Aerospace
The service faces an "axis of upheaval," Gen. Randy George said Tuesday.