Back to news

March 5, 2024 | International, Naval

Rearming US Navy ships at sea is no longer an option, but a necessity

Opinion: Fortunately, rearming VLS cells at sea is not an impossible engineering problem.

https://www.defensenews.com/opinion/2024/03/05/rearming-us-navy-ships-at-sea-is-no-longer-an-option-but-a-necessity/

On the same subject

  • Delays Cause Two-Year, $1.5B Extension For F-35 Block 4

    May 13, 2020 | International, Aerospace

    Delays Cause Two-Year, $1.5B Extension For F-35 Block 4

    Steve Trimble The U.S. Government Accountability Office (GAO) said on May 12 that the Lockheed Martin F-35 Block 4 program must be extended two years due to development delays, adding $1.5 billion to the overall price tag. The original schedule called for completing the Block 4 modernization program in 2024, but the timeline must be extended to 2026, GAO said in the watchdog agency's annual review of the F-35 program. The F-35 Joint Program Office initially estimated the cost to develop all 66 new capabilities in Block 4 would be $10.6 billion. The two-year extension to deliver Block 4 raises the development cost to $12.1 billion, with another $3.4 billion budgeted to procure and insert the capabilities in future U.S. F-35s, GAO said. The Block 4 delays started in 2019. Lockheed planned to deliver the first eight Block 4 capabilities last year, but only one—the automatic ground collision avoidance system—entered service, GAO said. In another example, Lockheed delivered software last year to enable the interim full-motion video capability for the Marine Corps F-35Bs, but failed to deliver the associated hardware, the report said. As Block 4 capabilities have entered testing, the Defense Department's operational testers have noticed other problems. Some of the new capabilities have “caused issues” with existing F-35 functions that previously worked, GAO said. “The contractor had not performed adequate testing of the software before delivering it to the test fleet,” GAO said. For its part, the contractor acknowledged the issues and said they would conduct additional testing in software laboratories before releasing future software blocks, GAO added. https://aviationweek.com/aerospace/aircraft-propulsion/delays-cause-two-year-15b-extension-f-35-block-4

  • The Army wants to build a better signals intelligence force

    July 23, 2018 | International, C4ISR

    The Army wants to build a better signals intelligence force

    By: Mark Pomerleau The Army's top intelligence official signed the service's new signals intelligence strategy July 16, a move that defense leaders believe leaves the Army better situated to better fight despite electronic warfare and cyber attacks. The new strategy ensures "our readiness to provide timely and relevant SIGINT-support [and meet] the commander's information needs in a large scale combat operation against a sophisticated adversary,” Lt. Gen. Scott Berrier, said July 18 during an event on Capitol Hill hosted by the Association of Old Crows. Officials say the integration of SIGINT, electronic warfare and cyber is critical from a material, organization and doctrinal perspective. “Not only will our four lines of effort improve our SIGINT corps' capabilities and relevance in the face of rapid changes in the global security environment, it will also enable our electronic warfare and cyberspace effort to meet new challenges,” Berrier said. The four initiatives in the new strategy include: - Organizing and building the Army SIGINT force, - Educating the force, - Equipping the force, and - Developing doctrine. The new strategy increases the Army's ability to collect intelligence against peer adversaries, such as China and Russia, and provides a firm foundation for successful electronic warfare and cyber operations, Berrier said. A key component of the convergence includes the new Terrestrial Layer System (TLS), a SIGINT/EW system projected to be fielded on vehicles and used by new military intelligence-electronic warfare (MI-EW) companies the Army is working to stand up. The Army wants SIGINT, electronic warfare and cyber systems on the same platforms in the air and ground domain, Maj. Gen. Robert Walters, commander of the Intelligence Center of Excellence, said at the event. These systems, Berrier said, should be able to not only sense the environment but employ some type of action such as electronic attack or cyber capability. Why converge? Officials have stressed repeatedly in the last year the need for colleagues in similar disciplines throughout the Army to stay in touch and reap the mutually beneficial equities on behalf of commanders in the field. Lt. Gen. Stephen Fogarty, the head of Army Cyber Command, said commanders shouldn't have to have something explained to them by the EW guy, the SIGINT guy and then the cyber guy. “What we decided is there's a better way, we have to pull it all together” for the commander, he said at the event. “We're going to have to work together because we all operate in the same space. And so do we really need three separate tools to plan operations in the spectrum? My argument would be no.” From an organizational perspective, the 29 series electronic warfare personnel will have deep knowledge in both cyber and electromagnetic spectrum operations. On the materiel side, especially with programs like the Terrestrial Layer System, the cyber and intel community are meeting regularly to integrate their requirements, officials said. In addition, Maj. Gen. John Morrison, commander of the Cyber Center of Excellence, told reporters in June that the Intelligence Center of Excellence is working with the Cyber Center to help ensure integrated formation and integrated capabilities. https://www.c4isrnet.com/intel-geoint/2018/07/19/the-army-wants-to-build-a-better-signals-intelligence-force/

  • The US Army sees a future of robots and AI. But what if budget cuts and leadership changes get in the way?

    January 11, 2022 | International, Land, C4ISR

    The US Army sees a future of robots and AI. But what if budget cuts and leadership changes get in the way?

    Four years into Army Futures Command, experts say the effort is on track, but they warn that leadership changes, potential budget cuts and a few contracting and technological hiccups could put it at risk.

All news