Back to news

April 21, 2020 | International, Aerospace, Naval, Land, C4ISR, Security

Pentagon Pumps $3B Into Industry As COVID-19 Delays Loom

PENTAGON: The Pentagon's acquisition chief today said she expects major defense programs to be delayed by around three months due to COVID-19 closures and disruptions, while DoD rushes to pump $3 billion into the defense industry to bolster programs at greatest risk.

Speaking to reporters here this morning, Lord said she expects to have to ask the White House and Congress for “billions” more to reimburse contractors affected by work delays and broken supply chains. “We believe it will cost us something,” she said, declining to get any more specific than “billions” of dollars.

The months-long delays to programs will likely be spread throughout the defense industry as small parts suppliers shut down operations for days or weeks at a time. “We're looking at schedule delays and inefficiencies and so forth: this isn't about a particular program.” Lord singled out “a slowdown in the shipyards, to an extent. Aviation is actually the most highly impacted sector we have right now.”

It's unclear what programs are at highest risk, but the Navy has been bullish on speeding up its new frigate program to award contracts some time this summer. If work slowdowns continue, that could be pushed further down the road. The Army and Navy have also been moving ahead on their nascent hypersonic weapons program, with a series of critical tests planned this year.

Lord pointedly suggested that large defense companies need to start pushing more money into their supplier base to ensure small parts suppliers don't go out of business, further impacting new programs and ongoing maintenance efforts. She did praise Lockheed and Boeing for increasing cash flow to lower-tier suppliers, then not-so-subtly says, she is “hoping for similar public announcements from other major primes.”

Last month, Lockheed said it would advance more than $100 million to suppliers hurt by the slowdown, and this week Boeing said it was reopening the Philadelphia-area facility where it makes the Chinook, the V-22 Osprey and other helicopters.

The Pentagon is starting to award higher progress payment rates this week, pumping $3 billion dollars in increased cash flow to industry. “We try to anticipate the problems and work with the companies to keep going to the greatest degree possible,” Lord said.

As part of that effort, DoD's first priority is the modernization process of the nuclear triad, she said: “we look at the Missile Defense Agency, we look at the critical capabilities. We're looking where the greatest pain points are.”

While she singled out Lockheed and Boeing, shipbuilder Huntington Ingalls is making a push to speed up contracts and get money into the hands of sub-tier suppliers early, in order to ensure companies way down the supply base food chain can continue chugging along.

In a recent interview, company representatives told me they've reached out to over 2,000 suppliers in 48 of the 50 US states. “We need their products today, but we also need them in 90 days, so we want to help them brave the storm,” said Lucas Hicks, vice president of new construction aircraft carrier programs. “We've actually changed some payment terms on some of our supplier contracts to try to make sure that we can front them what they need to stay afloat. We're doing some creative stuff to try and help them be able to weather the storm.”

The Department's efforts to backstop the defense industrial base while taking steps to protect its workforce and purchase critical protective clothing like facemasks is still in its relative stages, despite the COVID-19 pandemic having been with us for months.

“We are just really beginning to pick up momentum,” Lord said.

https://breakingdefense.com/2020/04/pentagon-pumps-3b-into-industry-as-covid-19-delays-loom

On the same subject

  • US Air Force eyes NGAD deliveries by 2030. Can it be done?

    September 27, 2022 | International, Aerospace

    US Air Force eyes NGAD deliveries by 2030. Can it be done?

    "The odds are against it happening" by 2030, John Venable of the Heritage Foundation said. "In the last 25 or 30 years, nothing's come in on time.'€

  • Contract Awards by US Department of Defense - December 14, 2020

    December 17, 2020 | International, Aerospace, Naval, Land, C4ISR, Security

    Contract Awards by US Department of Defense - December 14, 2020

    AIR FORCE Northrop Grumman Systems Corp., Clearfield, Utah, has been awarded a $185,700,000 indefinite-delivery/indefinite-quantity contract for the A-10 Aircraft Structural Integrity Program (ASIP) Legacy VII. This contract provides for sustaining engineering services of A-10 aircraft. Work will be performed in Clearfield, Utah, and is expected to be completed by Dec. 13, 2030. This award is the result of a sole-source acquisition. Fiscal 2021 operation and maintenance funds in the amount of $6,480,694 are being obligated at the time of award. The Air Force Life Cycle Management Center, Hill Air Force Base, Utah, is the contracting activity (FA8202-21-D-0001). Northrop Grumman Systems Corp., Linthicum Heights, Maryland, has been awarded a $163,650,543 requirements contract for the supply chain management of the APY-1/2 surveillance radar systems used on Airborne Warning and Control Systems aircraft. The contract provides for repairs, sustaining spares and engineering services relating to the APY-1/2 systems. Work will be performed in Linthicum Heights, Maryland, and is expected to be completed Sept. 9, 2028. This award is the result of a sole-source acquisition. Fiscal 2021 defense working capital funds are being used and no funds are being obligated at the time of the award. The Air Force Sustainment Center, Robins Air Force Base, Georgia, is the contracting activity (FA8524-21-D-0006). The Boeing Co., St. Louis, Missouri, has been awarded a $79,569,583 firm-fixed-price contract for F-15 Eagle Passive Active Warning and Survivability System low rate initial production. Work will be performed in San Antonio, Texas, and is expected to be completed by Dec. 31, 2026. This award is the result of a sole-source acquisition. Fiscal 2020 production funds in the full amount are being obligated at the time of award. The Air Force Life Cycle Management Center, Wright-Patterson Air Force Base, Ohio, is the contracting activity (FA8634-21-C-2702). Northrop Grumman Systems Corp., McLean, Virginia, has been awarded a $13,464,704 requirements contract for the repairs, sustaining spares and engineering services relating to the Aircraft Alerting Communication Electromagnetic Pulse system. Work will be performed in Albuquerque, New Mexico, and is expected to be completed by Sept. 9, 2028. This award is the result of a sole-source acquisition. Fiscal 2021 defense working capital funds will be used with no funds being obligated at the time of award. The Air Force Sustainment Center, Robins Air Force Base, Georgia, is the contracting activity (FA8524-21-D-0001). DEFENSE LOGISTICS AGENCY Science Applications International Corp., Fairfield, New Jersey, has been awarded a maximum $90,000,000 firm-fixed-price contract for facilities maintenance, repair and operations items. This was a sole-source acquisition using justification 10 U.S. Code 2304 (c)(1), as stated in Federal Acquisition Regulation 6.302-1. This is a one-year bridge contract with no option periods. Locations of performance are New Jersey, Hawaii, Guam and the Kwajalein Atoll, with a Dec. 14, 2021, performance completion date. Using military services are Army, Navy, Air Force, Marine Corps and Coast Guard. Type of appropriation is fiscal 2021 through 2022 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE8E3-21-D-0004). NAVY Raytheon Missiles and Defense, Tewksbury, Massachusetts, was awarded a $59,414,933 firm-fixed-price, cost-plus-incentive-fee, cost-plus-fixed-fee, and cost modification to previously awarded contract N00024-17-C-5145 to exercise options for DDG 1000 ship class integrated logistics support, engineering services and procurement of M5 call servers. The total ship activation (TSA) contract includes mission system activation and hull mechanical and electrical activation efforts to include waterfront integration, activation and test of Zumwalt class mission systems and mission system equipment at the system and subsystem levels; development and conduct of the Zumwalt class TSA test program; personnel, program management, planning, training and other efforts required to effectively support the execution of the Zumwalt class TSA; development and review of design drawings, technical data packages, installation control drawings and change documentation in support of Zumwalt class TSA; and development and implementation of government-approved proposed changes and the implementation of Zumwalt class cybersecurity/information assurance requirements. Work will be performed in San Diego, California (42%); Portsmouth, Rhode Island (27%); Tewksbury, Massachusetts (22%); Bath, Maine (7%); Ft. Wayne, Indiana (1%); and Marlboro, Massachusetts (1%), and is expected to be completed by December 2021. Fiscal 2020 shipbuilding and conversion (Navy); fiscal 2021 research, development, test and evaluation (Navy); and fiscal 2021 other procurement (Navy), funding in the amount of 5,489,262 will be obligated at time of award and will not expire at the end of the current fiscal year. This contract was procured under the statutory authority of 10 U.S. Code 2304(c)(1); only one responsible source and no other supplies or services will satisfy agency requirements. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. (Awarded Dec. 11, 2020) BAE Systems, Information and Electronic Systems Integration Inc., Greenlawn, New York, is awarded an $18,003,287 firm-fixed-price, indefinite-delivery/indefinite-quantity contract. This contract provides for the production, test and delivery of up to five Mode 5 capable AN/APX-117A(V) systems; one Mode 5 capable AN/APX-118A(V) system; 308 Mode 5 capable AN/APX-123A(V) common identification friend or foe digital transponder systems; 289 Mode 5 kits; and associated shop replaceable assemblies and repairs incident to modification in support of fixed and rotary winged aircraft for the Navy, Army and non-Department of Defense participants. Work will be performed in Greenlawn, New York (85%); and Austin, Texas (15%), and is expected to be completed in December 2026. No funds will be obligated at time of award. Funds will be obligated on individual orders as they are issued. This contract was not competitively procured pursuant to Federal Acquisition Regulation 6.302-1. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity (N00019-21-D-0008). Raytheon Missiles and Defense, Tucson, Arizona, is awarded a $17,765,396 cost-plus-fixed-fee modification to previously awarded contract N00024-16-C-5433 to exercise options in support Evolved SeaSparrow missile design agent, in-service support and technical engineering support services. Work will be performed in Tucson, Arizona (91%); Hengelo Ov, Netherlands (2%); Raufoss, Norway (2%); Ottobrunn, Germany (1%); Richmond, Australia (1%); and various locations with less than 1% each (3%), and is expected to be completed by June 2021. This contract combines purchases for the U.S. government and other country funds (NATO consortium members, non-Foreign Military Sales (FMS) (99%); and the government of Japan (1%) under the FMS program. Fiscal 2021 other country funds in the amount of $9,772,474 (55%); 2021 weapons procurement (Navy) funds in the amount of $5,127,125 (29%); 2020 weapons procurement (Navy) funds in the amount of $2,354,250 (13%); 2021 research, development, testing and evaluation (Navy) funds in the amount of $399,547 (2%); and FMS (Japan) funds in the amount of $112,000 (1%) will be obligated at time of award and will not expire at the end of the current fiscal year. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. GBD JV,* Aberdeen, Maryland, is being awarded a $13,000,000 firm-fixed-price modification to increase the maximum dollar value of an indefinite-delivery/indefinite-quantity contract for new paving, paving repair and/or replacement of various types of paving within Naval Facilities Engineering Command (NAVFAC) Washington area of responsibility (AOR). The work to be performed provides for new paving, paving repair and/or replacement of various types of paving such as roadways, airfields, sidewalks, curbs, gutters, etc. Other incidental types of work, including but not limited to, demolition, site preparations and site drainage are also included in the scope of work. Paving and associated work may be ordered for industrial, commercial and residential locations indicated with each task order. After award of this modification, the total cumulative contract value will be $63,000,000. Work will be performed in the NAVFAC Washington AOR, including but not limited to, Maryland (40%); Virginia (40%); and Washington, D.C. (20%). The term of the contract is not to exceed 48 months with an expected completion date of April 2021. No funds will be obligated at time of award and funds will be obligated on individual task orders as they are issued. Future task orders will be primarily funded by military construction (Navy); operation and maintenance (O&M) (Navy); O&M (Marine Corps); and Navy working capital funds. NAVFAC Washington, Washington, D.C., is the contracting activity (N40080-17-D-0033). Forward Slope Inc., San Diego, California, is being awarded an $11,323,595 modification P00008 to previously awarded requirements-type contract N66001-18-D-0117 to provide command, control, communications, intelligence, surveillance and reconnaissance (C4ISR) planning and design services in support of shore installation projects. This one-year modification increases the overall value of the existing contract to $34,867,630. The period of performance is from Jan. 11, 2021, through Jan. 10, 2022. Work will be performed at the contractor's facilities in San Diego, California (50%); and Hawaii (50%). Contract funds will not expire at the end of the fiscal year. No funds will be obligated at the time of award. Fiscal 2021 operation and maintenance (Navy) funds will be obligated as individual task orders are issued. This contract was originally competitively procured via request for proposal N66001-17-R-0002 published on the beta.SAM.gov website. Eight offers were received and one was selected for award. The Naval Information Warfare Center Pacific, San Diego, California, is the contracting activity (N66001-18-D-0117). ARMY InSap Services Inc., Marlton, New Jersey, was awarded a $24,507,978 modification (BA0250) to contract W91QUZ-11-D-0017 for enterprise application services support to the Army's Logistics Modernization Program. Work will be performed in Marlton, New Jersey, with an estimated completion date of Dec. 14, 2020. Fiscal 2020 civil consolidated working funds in the amount of $10,394,401 were obligated at the time of the award. The U.S. Army Contracting Command, Rock Island Arsenal, Illinois, is the contracting activity. Oakland Consulting Group, Lanham, Maryland, was awarded a $12,407,852 modification (BA0236) to contract W91QUZ-11-D-0018 for enterprise application services support to the Army's Logistics Modernization Program. Work will be performed in Lanham, Maryland, with an estimated completion date of March 31, 2021. Fiscal 2020 civil consolidated working funds in the amount of $4,359,142 were obligated at the time of the award. The U.S. Army Contracting Command, Rock Island Arsenal, Illinois, is the contracting activity. Avion Solutions Inc., Huntsville, Alabama, was awarded an $8,820,564 modification (000337) to contract W31P4Q-18-A-0047 for logistics support for the Unmanned Aircraft Systems project manager's office. Work will be performed in Huntsville, Alabama, with an estimated completion date of Aug. 31, 2021. Fiscal 2021 operation and maintenance (Army) funds in the amount of $8,820,564 were obligated at the time of the award. The U.S. Army Contracting Command, Redstone Arsenal, Alabama, is the contracting activity. *Small business https://www.defense.gov/Newsroom/Contracts/Contract/Article/2446305/source/GovDelivery/

  • The Navy's Fighter Shortage Is Finally, Slowly Improving

    August 21, 2018 | International, Aerospace, Naval

    The Navy's Fighter Shortage Is Finally, Slowly Improving

    By Kyle Mizokami The U.S. Navy's horrible fighter availability rate is gradually improving thanks to increased funding for fighter maintenance. At one point in 2017, just one in three F/A-18 Super Hornet fighters was available, a number that's increased to nearly half of all fighters. The problem is in large part due to past budget shortfalls and delayed introduction of the F-35 fighter jet. The U.S. Navy has 546 F/A-18E and F/A-18F Super Hornet fighters, larger, beefier, slightly stealthier versions of the original F/A-18 Hornet. Aircraft readiness rates, or the percentage of aircraft ready for deployment, should typically be north of seventy five percent, depending on type of aircraft, the complexity of the aircraft systems, and the age of the fleet. In 2017, the Navy's Super Hornet fleet hovered around 30 percent readiness, a shockingly low number the service blamed on minimal maintenance budgets and non-stop operations. The Navy struggled to place flight-capable aircraft with squadrons deploying on aircraft carriers. On the outside things looked fairly normal, as carriers went to sea with flight decks filled with Super Hornets. Behind the scenes however non-deployed squadrons suffered, acting as spare parts donors for deployment-bound ships. This cascading effect had negative implications for stateside squadrons and pilot training. According to DefenseNews, Secretary of the Navy Richard Spencer cited increased maintenance budgets over the past two years as a major part of the turnaround, allowing the service to fund repairs and spare parts. The service also streamlined maintenance processes, avoiding duplication and increasing efficiency. The maintenance crisis was caused by several problems. The high demand for strike fighters, particularly for combat operations against the Islamic State, increased the amount of wear and tear on the Super Hornet fleet. Super Hornets also act as aerial refueling tankers, increasing flight hours and wear and tear on the platform. Meanwhile the Navy struggled to operate within the budget mandated by the 2011 Budget Control Act that trimmed federal spending. Making matters worse, so-called "continuing resolutions" passed during times of budget bickering to keep government going were an inefficient means of spending money and played havoc with the Pentagon's budget. Another problem that indirectly cause the crisis: a delay in the introduction of the U.S. Navy's version of the Joint Strike Fighter, the F-35C. The F-35C, meant to replace older F/A-18C Hornet fighters, is now at least three years behind schedule. As the chart above illustrates, the Navy originally expected the F-35C to be initial operations capable—when the first Navy squadron is at least partially combat-capable—in late 2015. That date has gradually slipped to late 2018 or early 2019. On the outside things looked fairly normal, as carriers went to sea with flight decks filled with Super Hornets. Behind the scenes however non-deployed squadrons suffered, acting as spare parts donors for deployment-bound ships. This cascading effect had negative implications for stateside squadrons and pilot training. According to DefenseNews, Secretary of the Navy Richard Spencer cited increased maintenance budgets over the past two years as a major part of the turnaround, allowing the service to fund repairs and spare parts. The service also streamlined maintenance processes, avoiding duplication and increasing efficiency. The maintenance crisis was caused by several problems. The high demand for strike fighters, particularly for combat operations against the Islamic State, increased the amount of wear and tear on the Super Hornet fleet. Super Hornets also act as aerial refueling tankers, increasing flight hours and wear and tear on the platform. Meanwhile the Navy struggled to operate within the budget mandated by the 2011 Budget Control Act that trimmed federal spending. Making matters worse, so-called "continuing resolutions" passed during times of budget bickering to keep government going were an inefficient means of spending money and played havoc with the Pentagon's budget. Another problem that indirectly cause the crisis: a delay in the introduction of the U.S. Navy's version of the Joint Strike Fighter, the F-35C. The F-35C, meant to replace older F/A-18C Hornet fighters, is now at least three years behind schedule. As the chart above illustrates, the Navy originally expected the F-35C to be initial operations capable—when the first Navy squadron is at least partially combat-capable—in late 2015. That date has gradually slipped to late 2018 or early 2019. As a result of this delay, the Navy was forced to extend the lives of five squadrons of older -C model Hornets while it waited for the F-35C. That work added to the burden of Navy maintenance units already working to keep Super Hornets flying. In addition to the Navy's maintenance work, Boeing is set to take 40 to 50 Super Hornets a year and upgrade them to the new Block III configuration. DefenseNews says this will also bring the jets in the worst shape back to flying condition. In the long term F-35C production should ease the burden on the Super Hornet community, as the fifth generation fighter will eventually equip half of the strike fighter squadrons deployed on U.S. Navy carriers. The executive branch's 2019 defense budget also plans for an additional 110 Super Hornets over five years. Finally, the Navy plans to acquire a small fleet of MQ-25 Stingray unmanned aerial refueling aircraft to take over tanking duties from the overworked strike fighters. Full article: https://www.popularmechanics.com/military/aviation/a22778556/us-navy-fighter-shortage-progress

All news