Lockheed slated to miss F-35 delivery target in 2020 as supply chain struggles to keep up

By:   20 hours ago

WASHINGTON — Lockheed Martin will throttle back the pace of F-35 production on May 23, leaving it anywhere from 18 to 24 jets short of the 141 scheduled for delivery this year.

The COVID-19 pandemic has made it more difficult for Lockheed's supply chain to make components on time, and as a result the company is moving to an adjusted work schedule where production will slow over the next three months, said Greg Ulmer, Lockheed's vice president for the F-35 program.

Ultimately, Lockheed aims to accelerate production as soon as possible and hopes to decrease the number of aircraft that will delivered late. However, Ulmer said there are too many variables to say precisely how long buyers will be left waiting for their F-35s.

“If I have the ability to speed up or recover sooner, then I will do so,” Ulmer said. “If there are other unknown COVID-19 impacts that I don't know about that come on the horizon — I don't know that either. ... As we go forward, probably late summer or early fall, we'll have a pretty good sense of where we're going to be.”

Beginning on May 23, Lockheed will divide the approximately 2,500 employees who staff the F-35 production line in Fort Worth, Texas, into three groups, moving them to new schedule where each group works for two weeks and then has a week off. After one three-week rotation, the company will determine whether the system is successful and can either alter the schedule or continue until Sept. 4, it said in a statement.

Rotating smaller groups of employees on the line allows Lockheed to move to a slower pace of operations while at the same time ensuring that workers retain their expertise and don't need to be retrained when the production rate returns to normal, Ulmer said. “It really maximizes our ability to recover production on the backside and retain our workforce with no loss of learning.”

Lockheed Martin executives first disclosed that F-35 deliveries could be delayed during an April 21 earnings call with investors.

“There are local distancing requirements that are being more stringently applied across the globe. There is workforce disruption,” Kenneth Possenriede, the company's chief financial officer, said at the time. “We've actually had some issues with shipping constraints.”

Most of the supply chain pressure on the program stems from constraints on low-tier suppliers that produce components that feed into larger portions of the F-35. While the production line tries to do as much work on each section as possible, workers are having to slow down and wait for missing parts to arrive, Ulmer said.

Lockheed has also had challenges getting connectors for the jet on time — another problem that makes it difficult for the company to merge F-35 sub-assemblies into a finished aircraft, Ulmer said.

Once aircraft are completed and go through acceptance testing, the sequence of deliveries will remain the same, he said.

The slowdown of the F-35's production rate comes days after President Donald Trump voiced support for moving more of the jet's production to the United States. Currently, international partners who helped fund development of the F-35 can compete for work on the jet, reducing the cost of the aircraft and giving foreign buyers an industrial incentive to support the program.

“The problem is if we have a problem with a country, you can't make the jet. We get parts from all over the place. It's so crazy. We should make everything in the United States,” Trump said on Thursday.

However, the industrial challenges currently faced by Lockheed do not appear to be caused by the international supply base. Ulmer said European suppliers, who were hardest hit before the United States, are now rebounding from the pandemic.

“I really see Europe kind of [on the] leading edge of the recovery side of this,” he said.

In particular, northern Italy struggled with high numbers of confirmed COVID-19 cases, leading Italian defense firm Leonardo, which runs an F-35 final assembly and check out plant in Cameri, to shut down operations over a two day period in March to clean the facility. With the number of new cases receding, Italy began reopening nonessential businesses this month.

“Leonardo today is north of 90 percent manned, fully operating. They're pretty much back to normal operations,” Ulmer said.

The ongoing expulsion of Turkish suppliers from the F-35 program is also unlikely to be affected by the production slowdown at Fort Worth, as Lockheed has already identified companies to take over that work, he said. “With the vast majority of those, that alternate sourcing has been accomplished. I really don't see this as an impact to that."

Ramping production back up

Unless COVID-19 cases spike in the coming months, Lockheed believes it will be able to return workers to a normal production schedule in the late summer or early fall.

What will vary is timing for when suppliers can return to their usual production rates, and whether those suppliers have the capacity to expedite the manufacturing of key parts, Ulmer said. Once the supply chain has fully recovered, it will take the Fort Wort line two to three months to resume full rate production.

“There are 1,900 suppliers across the program” in the United States, Ulmer said. “So we take all that information in, we determine what rate they can deliver to, we determine if they have any kind of constraints we can help them deal with, and then we have to balance that into the production system to dial in the production rate we can execute.”

“I am optimistic that the majority of industry is on the backside. I'm reluctant to say that because there could be a rebound,” Ulmer said, “but we're at the very back end of the impact.”

https://www.defensenews.com/breaking-news/2020/05/19/lockheed-to-slow-f-35-production-as-supply-chain-struggles-to-keep-up

On the same subject

  • Britain receives first ‘Poseidon’ aircraft in bid to restore submarine-hunting muscle

    February 5, 2020 | International, Aerospace

    Britain receives first ‘Poseidon’ aircraft in bid to restore submarine-hunting muscle

    By: Andrew Chuter LONDON – The British on Tuesday began to restore their once-formidable capabilities for maritime patrol with the arrival to the Royal Air Force base at Kinloss, Scotland, of the first of a fleet of Boeing P-8A Poseidon jets. Flown by a crew from the RAF's CXX Squadron, the first of nine P-8A's, ordered by the British in 2016 at a cost of £3 billion ($3.9 billion), arrived pretty much on cue at the Kinloss base that will be its temporary home until infrastructure and other work at its permanent base at Lossiemouth is completed later this year. A recent tweet RAF tweet said the aircraft had already operated some tactical missions. Doug Barry, the senior air analyst at the International Institute for Strategic Studies think tank in London, says the aircraft landing in Scotland is a big moment for the Royal Air Force. “The arrival of the first P-8A is symbolic in that it marks the UK beginning to get back into the fixed-wing anti-submarine warfare business after a gap of a decade,” he said. The British are scheduled to ramp up their P-8A numbers rapidly as a resurgence in Russian submarine activity continues to challenge Western resources in the sector. A second aircraft is due to arrive at Lossiemouth by the end of March, three further P-8A's will be handed over by the end of the year with the four remaining machines all due to arrive by the fourth quarter of 2021. Full operating capability is scheduled for 2024. The aircraft are known as Poseidon MRA Mk1 in RAF service. Late last year, commenting on Russian nuclear submarine activity, top US Navy officer Adm. James Foggo, commander of US Naval Forces Europe and Africa, reported 2019 as being “one of the busiest years that I can remember, and I've been doing this since 1983.” First Sea Lord Adm. Tony Radakin said: “The arrival of the first Poseidon marks a significant upgrade in the UK's ability to conduct anti-submarine operations. This will give the UK the ability to conduct long-range patrols and integrate seamlessly with our NATO allies to provide a world-leading capability.” In co-operation with the US sea service and the Royal Norwegian Air Force, who have purchased five P-8A's, the RAF will attempt to plug any gaps in anti-submarine defenses in the North Atlantic. One of the British P-8A's main tasks will be to provide cover for Royal Navy Trident missile submarines emerging and returning to their base at Faslane in Scotland. Barrie said that for the last decade the “UK has had to look elsewhere to support the deployment of its strategic deterrent to try to ensure there was no unwanted company.” The US, France, Canada and others have all had to step in at times to provide reconnaissance and other capabilities to help glug the hole in British fixed-wing, anti-submarine defenses caused when a government strategic defence and security review in 2010 controversially cancelled the MRA4 program without looking to purchase a replacement. The British have sought to retain their maritime patrol skills over the last few years by placing aircrew and operators with allies like the United States. The new aircraft entered service with the RAF late last year but the platform has until now been based at the Jacksonville, Florida, naval air station where British crew training is taking place ahead of eventually transitioning to Lossiemouth. Training and simulation facilities are part of a new £132 million ($171 million) infrastructure project at Lossiemouth jointly funded by the MoD and Boeing, which is scheduled for completion later this year. Flight operations and planning, maintenance, crew rooms and space for three aircraft will also be included in the facility. More than 200 Boeing employees will be permanently based on the base. Some £470 million ($612 mission) in total is being invested in Lossiemouth, which is also home to part of the Typhoon fighter fleet, upgrading runways, building a new air traffic tower and other improvements. https://www.defensenews.com/global/europe/2020/02/04/britain-receives-first-poseidon-aircraft-in-bid-to-restore-submarine-hunting-muscle

  • Kratos Receives $37.7 Million Skyborg Program Contract Award from USAF Advanced Aircraft Office

    December 9, 2020 | International, Aerospace

    Kratos Receives $37.7 Million Skyborg Program Contract Award from USAF Advanced Aircraft Office

    San Diego, December 8, 2020 (GLOBE NEWSWIRE) -- Kratos Defense & Security Solutions, Inc. (NASDAQ: KTOS), a leading National Security Solutions provider and industry-leading provider of high-performance, jet-powered unmanned aerial systems, announced today that Kratos has received a $37,771,577 award from the AFLCMC/WA Advanced Aircraft Program Executive Office for the Skyborg Delivery Order (DO) 2 contract to integrate, test, and deliver XQ-58A Valkyrie aircraft. Steve Fendley, President of Kratos Unmanned Systems Division, said, “Kratos is excited to announce the receipt of the Skyborg DO 2 contract, meeting a long-term strategic objective. The Skyborg Program, one of three USAF Vanguard Programs, is focused on expanding the envelope of the application of unmanned aircraft use, particularly with respect to Artificial Intelligence. Kratos XQ-58A has been flying since March of 2019, approximately 30 months after aircraft conception, and was designed specifically for these applications and the ability to support missions from ISR to Strike in manned-unmanned teaming scenarios or in unmanned only mission sets. These capabilities are intended to substantially increase the effectiveness of our country's military mission sets, while at the same time reducing risk to the exquisite assets and manned elements—saving resources and, most importantly, lives.” The contract includes three phases of design, integration, and flight testing of the Kratos XQ-58A Valkyrie system, integrating multiple customer-defined mission payloads and customer-defined autonomy in coordination/cooperation with the Skyborg System Design Agent company, Leidos. Kratos currently works in partnership with Leidos' Dynetics on the Gremlins Program. About Kratos Defense & Security Solutions Kratos Defense & Security Solutions, Inc. (NASDAQ:KTOS) develops and fields transformative, affordable technology, platforms and systems for United States National Security related customers, allies and commercial enterprises. Kratos is changing the way breakthrough technology for these industries are rapidly brought to market through proven commercial and venture capital backed approaches, including proactive research and streamlined development processes. At Kratos, affordability is a technology, and we specialize in unmanned systems, satellite communications, cyber security/warfare, microwave electronics, missile defense, hypersonic systems, training, combat systems and next generation turbo jet and turbo fan engine development. For more information, please visit www.KratosDefense.com. Notice Regarding Forward-Looking Statements Certain statements in this press release may constitute “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. These forward-looking statements are made on the basis of the current beliefs, expectations and assumptions of the management of Kratos and are subject to significant risks and uncertainty. Investors are cautioned not to place undue reliance on any such forward-looking statements. All such forward-looking statements speak only as of the date they are made, and Kratos undertakes no obligation to update or revise these statements, whether as a result of new information, future events or otherwise. Although Kratos believes that the expectations reflected in these forward-looking statements are reasonable, these statements involve many risks and uncertainties that may cause actual results to differ materially from what may be expressed or implied in these forward-looking statements. For a further discussion of risks and uncertainties that could cause actual results to differ from those expressed in these forward-looking statements, as well as risks relating to the business of Kratos in general, see the risk disclosures in the Annual Report on Form 10-K of Kratos for the year ended December 29, 2019, and in subsequent reports on Forms 10-Q and 8-K and other filings made with the SEC by Kratos. Press Contact: Yolanda White 858-812-7302 Direct Investor Information: 877-934-4687 investor@kratosdefense.com View source version on Kratos Defense & Security Solutions, Inc.: https://ir.kratosdefense.com/news-releases/news-release-details/kratos-receives-377-million-skyborg-program-contract-award-usaf

  • National advanced mobility consortium selects Oshkosh Defense to produce new cold weather all-terrain vehicle prototype

    April 8, 2021 | International, Land

    National advanced mobility consortium selects Oshkosh Defense to produce new cold weather all-terrain vehicle prototype

    The CATV is a new program for a tracked vehicle that operates in extreme cold weather or arctic conditions and is designed to replace the Small Unit Support Vehicles that have...

All news