May 20, 2020 | International, Aerospace

Lockheed slated to miss F-35 delivery target in 2020 as supply chain struggles to keep up

By:   20 hours ago

WASHINGTON — Lockheed Martin will throttle back the pace of F-35 production on May 23, leaving it anywhere from 18 to 24 jets short of the 141 scheduled for delivery this year.

The COVID-19 pandemic has made it more difficult for Lockheed's supply chain to make components on time, and as a result the company is moving to an adjusted work schedule where production will slow over the next three months, said Greg Ulmer, Lockheed's vice president for the F-35 program.

Ultimately, Lockheed aims to accelerate production as soon as possible and hopes to decrease the number of aircraft that will delivered late. However, Ulmer said there are too many variables to say precisely how long buyers will be left waiting for their F-35s.

“If I have the ability to speed up or recover sooner, then I will do so,” Ulmer said. “If there are other unknown COVID-19 impacts that I don't know about that come on the horizon — I don't know that either. ... As we go forward, probably late summer or early fall, we'll have a pretty good sense of where we're going to be.”

Beginning on May 23, Lockheed will divide the approximately 2,500 employees who staff the F-35 production line in Fort Worth, Texas, into three groups, moving them to new schedule where each group works for two weeks and then has a week off. After one three-week rotation, the company will determine whether the system is successful and can either alter the schedule or continue until Sept. 4, it said in a statement.

Rotating smaller groups of employees on the line allows Lockheed to move to a slower pace of operations while at the same time ensuring that workers retain their expertise and don't need to be retrained when the production rate returns to normal, Ulmer said. “It really maximizes our ability to recover production on the backside and retain our workforce with no loss of learning.”

Lockheed Martin executives first disclosed that F-35 deliveries could be delayed during an April 21 earnings call with investors.

“There are local distancing requirements that are being more stringently applied across the globe. There is workforce disruption,” Kenneth Possenriede, the company's chief financial officer, said at the time. “We've actually had some issues with shipping constraints.”

Most of the supply chain pressure on the program stems from constraints on low-tier suppliers that produce components that feed into larger portions of the F-35. While the production line tries to do as much work on each section as possible, workers are having to slow down and wait for missing parts to arrive, Ulmer said.

Lockheed has also had challenges getting connectors for the jet on time — another problem that makes it difficult for the company to merge F-35 sub-assemblies into a finished aircraft, Ulmer said.

Once aircraft are completed and go through acceptance testing, the sequence of deliveries will remain the same, he said.

The slowdown of the F-35's production rate comes days after President Donald Trump voiced support for moving more of the jet's production to the United States. Currently, international partners who helped fund development of the F-35 can compete for work on the jet, reducing the cost of the aircraft and giving foreign buyers an industrial incentive to support the program.

“The problem is if we have a problem with a country, you can't make the jet. We get parts from all over the place. It's so crazy. We should make everything in the United States,” Trump said on Thursday.

However, the industrial challenges currently faced by Lockheed do not appear to be caused by the international supply base. Ulmer said European suppliers, who were hardest hit before the United States, are now rebounding from the pandemic.

“I really see Europe kind of [on the] leading edge of the recovery side of this,” he said.

In particular, northern Italy struggled with high numbers of confirmed COVID-19 cases, leading Italian defense firm Leonardo, which runs an F-35 final assembly and check out plant in Cameri, to shut down operations over a two day period in March to clean the facility. With the number of new cases receding, Italy began reopening nonessential businesses this month.

“Leonardo today is north of 90 percent manned, fully operating. They're pretty much back to normal operations,” Ulmer said.

The ongoing expulsion of Turkish suppliers from the F-35 program is also unlikely to be affected by the production slowdown at Fort Worth, as Lockheed has already identified companies to take over that work, he said. “With the vast majority of those, that alternate sourcing has been accomplished. I really don't see this as an impact to that."

Ramping production back up

Unless COVID-19 cases spike in the coming months, Lockheed believes it will be able to return workers to a normal production schedule in the late summer or early fall.

What will vary is timing for when suppliers can return to their usual production rates, and whether those suppliers have the capacity to expedite the manufacturing of key parts, Ulmer said. Once the supply chain has fully recovered, it will take the Fort Wort line two to three months to resume full rate production.

“There are 1,900 suppliers across the program” in the United States, Ulmer said. “So we take all that information in, we determine what rate they can deliver to, we determine if they have any kind of constraints we can help them deal with, and then we have to balance that into the production system to dial in the production rate we can execute.”

“I am optimistic that the majority of industry is on the backside. I'm reluctant to say that because there could be a rebound,” Ulmer said, “but we're at the very back end of the impact.”

https://www.defensenews.com/breaking-news/2020/05/19/lockheed-to-slow-f-35-production-as-supply-chain-struggles-to-keep-up

On the same subject

  • GAO backs use of commercial satellites to host military payloads

    July 31, 2018 | International, Aerospace

    GAO backs use of commercial satellites to host military payloads

    by Sandra Erwin “Using hosted payloads may help facilitate a proliferation of payloads on orbit, making it more difficult for an adversary to defeat a capability." WASHINGTON — The Pentagon should use commercial satellites as host platforms for military sensors and communications packages, says a new Government Accountability Office report released on Monday. GAO auditors investigated the pros and cons of “hosted payloads” and agreed with what private satellite operators have been saying for years: The military can save money and get capabilities on-orbit faster by hitching rides on commercial satellites. The industry has been building huge spacecraft that have extra carrying capacity, and hosting national security payloads is viewed as a profitable business that also helps the military fill a need. The report says there are national security benefits to deploying military payloads on commercial satellites. “Using hosted payloads may also help facilitate a proliferation of payloads on orbit, making it more difficult for an adversary to defeat a capability.” Since 2009, DoD has used three commercially hosted payloads, with three more missions planned or underway through 2022. In 2011, the Air Force created a Hosted Payload Office to provide expertise and other tools to facilitate matching government payloads with commercial hosts. GAO found that defense programs using hosted payloads are not required and generally do not provide cost and technical data, or lessons learned, to the Hosted Payload Office. Having that information would “better position DoD to make informed decisions when considering acquisition approaches for upcoming space system designs.” The Pentagon has not been too keen on hosted payloads for several reasons, GAO noted. There is a perception among some defense officials that matching government payloads to commercial satellites is too difficult. Another concern is that DoD's knowledge on using hosted payloads is “fragmented, in part because programs are not required to share information.” DoD officials who spoke with GAO identified “logistical challenges to matching government payloads with any given commercial host satellite.” For example, they cited size, weight and power constraints as barriers to using hosted payloads. Some individual DoD offices have realized cost and schedule benefits, but “DoD as a whole has limited information on costs and benefits of hosted payloads,” said the report. Officials at the Office of the Secretary of Defense told GAO that “matching requirements between government payloads and commercial satellites is typically too difficult for programs to overcome.” DoD's Hosted Payload Office is “developing tools designed to help address these challenges,” said the report. Defense officials also argued that budget and planning processes are a hurdle. “This can complicate alignment with commercial timelines because the development of a government sensor would need to be underway well in advance of a decision to fund a commercially hosted payload approach.” Officials told GAO that it is possible to align government and commercial timelines. For example, the Missile Defense Agency adopted the commercial host's schedule to ensure its Space Based Kill Assessment payload was ready for integration and launch without delaying the host satellite or missing its ride to space. Similarly, the Defense Advanced Research Projects Agency has been able to align acquisition and development schedules with the commercial host. In its written comments in the report, DoD concurred with GAO's recommendations and noted that the Air Force Space and Missile Systems Center had initiated a major reorganization and that under the new organization, the Hosted Payload Office had changed and may not be the appropriate office for centralizing DoD-wide hosted payload knowledge. Language in the Fiscal Year 2019 National Defense Authorization Act directs the Pentagon to seize oversight of military investments in hosted payloads. https://spacenews.com/gao-backs-use-of-commercial-satellites-to-host-military-payloads/

  • Germany plans purchase of six IRIS-T air defence units - source

    June 13, 2023 | International, Land

    Germany plans purchase of six IRIS-T air defence units - source

    Germany aims to purchase six IRIS-T air defence systems for its air force at a total cost of some 900 million euros ($971.73 million), a defence source told Reuters ahead of a final decision by lawmakers on Wednesday.

  • The Green Heat Test Drive - call for proposals has been extended!/Banc d'essai énergie verte - appel de propositions prolongée!

    September 1, 2021 | International, Other Defence

    The Green Heat Test Drive - call for proposals has been extended!/Banc d'essai énergie verte - appel de propositions prolongée!

    The Green Heat: Low Carbon Energy Generation for Heating Existing Buildings Test Drive call for proposals has been extended! We are pleased to announce that the deadline to apply to the Green Heat Test Drive Call for Proposals (CFP) has been extended by three weeks. The deadline for application is now Tuesday, September 28, 2021. See the full Call for Proposals that was issued July 27, 2021, and explore how you can support environmental progress and contribute to this key energy initiative. In extending the deadline, the Department of National Defence (DND) is maximizing its chances of getting the best technology to solve the challenge of finding ways to convert its buildings to low carbon heating without requiring a major building retrofit, and address greenhouse gas (GHG) emissions. About the challenge: The Department of National Defence and the Canadian Armed Forces (DND/CAF) are looking to Test Drive creative energy generation solutions to pair up with existing heating systems to help lower our carbon footprint. Specifically, DND/CAF are seeking a large-scale, low carbon energy generation/transfer system for heating existing buildings by integrating with their current hydronic heat distribution systems. A test building has been selected in Kingston, Ontario, for a Design-Build team to design and install an innovative system, in order to assess the effectiveness and the costs of these integrated technologies, with the aim of reducing the energy demand and carbon footprint of DND/CAF's infrastructure portfolio. The potential funding for the Design-Build contract component of the project has been established in the range of $5,500,000. Interested in knowing more about this Test Drive? Please reach out to the Test Drive & Sandbox Team: IDEaSSandboxes-EnvironnementsprotegesIDEeS@forces.gc.ca The IDEaS Team Énergie Verte : Production d'énergie à faibles émissions de carbone pour le chauffage de b'timents existants – Appel de propositions prolongée! Nous sommes heureux d'annoncer que la date limite pour l'appel de propositions pour le Banc d'essai Énergie Verte a été prolongée de trois semaines. L'échéance pour présenter une demande est désormais fixée au mardi 28 septembre 2021. Consultez l'intégralité de l'appel de propositions publié le 27 juillet 2021 et découvrez comment vous pouvez soutenir le progrès environnemental et contribuer à cette initiative énergétique clé. En prolongeant la date limite, le ministère de la Défense nationale (MDN) maximise ses chances d'obtenir la meilleure technologie pour relever le défi de trouver des moyens de convertir ses b'timents au chauffage à faibles émissions de carbone sans nécessiter une rénovation majeure du b'timent, et de lutter à réduire les émissions de gaz à effet de serre (GES). À propos du défi : Le ministère de la Défense nationale et les Forces armées canadiennes (MDN/FAC) cherchent à tester des solutions créatives de production d'énergie à jumeler avec les systèmes de chauffage existants pour aider à réduire notre empreinte carbone. Plus précisément, le MDN et les FAC recherchent un système de production/transfert d'énergie à grande échelle et à faible émission de carbone pour le chauffage des b'timents existants; ce système serait intégré aux systèmes actuels de distribution du chauffage hydronique. Un b'timent d'essai a été sélectionné à Kingston, en Ontario, afin qu'une équipe de conception-construction conçoive et installe un système novateur. L'objectif est d'évaluer l'efficacité et les coûts de ces technologies intégrées, dans le but de réduire la demande d'énergie et l'empreinte carbone du portefeuille d'infrastructures du MDN et des FAC. Le financement possible pour le volet conception-construction du projet a été établi à environ 5 500 000 $. Vous souhaitez en savoir plus sur ce banc d'essai ? Veuillez contacter l'équipe Banc d'essai & Environnement Protégé : IDEaSSandboxes-EnvironnementsprotegesIDEeS@forces.gc.ca L'équipe IDEeS

All news