May 20, 2020 | International, Aerospace

Lockheed slated to miss F-35 delivery target in 2020 as supply chain struggles to keep up

By:   20 hours ago

WASHINGTON — Lockheed Martin will throttle back the pace of F-35 production on May 23, leaving it anywhere from 18 to 24 jets short of the 141 scheduled for delivery this year.

The COVID-19 pandemic has made it more difficult for Lockheed's supply chain to make components on time, and as a result the company is moving to an adjusted work schedule where production will slow over the next three months, said Greg Ulmer, Lockheed's vice president for the F-35 program.

Ultimately, Lockheed aims to accelerate production as soon as possible and hopes to decrease the number of aircraft that will delivered late. However, Ulmer said there are too many variables to say precisely how long buyers will be left waiting for their F-35s.

“If I have the ability to speed up or recover sooner, then I will do so,” Ulmer said. “If there are other unknown COVID-19 impacts that I don't know about that come on the horizon — I don't know that either. ... As we go forward, probably late summer or early fall, we'll have a pretty good sense of where we're going to be.”

Beginning on May 23, Lockheed will divide the approximately 2,500 employees who staff the F-35 production line in Fort Worth, Texas, into three groups, moving them to new schedule where each group works for two weeks and then has a week off. After one three-week rotation, the company will determine whether the system is successful and can either alter the schedule or continue until Sept. 4, it said in a statement.

Rotating smaller groups of employees on the line allows Lockheed to move to a slower pace of operations while at the same time ensuring that workers retain their expertise and don't need to be retrained when the production rate returns to normal, Ulmer said. “It really maximizes our ability to recover production on the backside and retain our workforce with no loss of learning.”

Lockheed Martin executives first disclosed that F-35 deliveries could be delayed during an April 21 earnings call with investors.

“There are local distancing requirements that are being more stringently applied across the globe. There is workforce disruption,” Kenneth Possenriede, the company's chief financial officer, said at the time. “We've actually had some issues with shipping constraints.”

Most of the supply chain pressure on the program stems from constraints on low-tier suppliers that produce components that feed into larger portions of the F-35. While the production line tries to do as much work on each section as possible, workers are having to slow down and wait for missing parts to arrive, Ulmer said.

Lockheed has also had challenges getting connectors for the jet on time — another problem that makes it difficult for the company to merge F-35 sub-assemblies into a finished aircraft, Ulmer said.

Once aircraft are completed and go through acceptance testing, the sequence of deliveries will remain the same, he said.

The slowdown of the F-35's production rate comes days after President Donald Trump voiced support for moving more of the jet's production to the United States. Currently, international partners who helped fund development of the F-35 can compete for work on the jet, reducing the cost of the aircraft and giving foreign buyers an industrial incentive to support the program.

“The problem is if we have a problem with a country, you can't make the jet. We get parts from all over the place. It's so crazy. We should make everything in the United States,” Trump said on Thursday.

However, the industrial challenges currently faced by Lockheed do not appear to be caused by the international supply base. Ulmer said European suppliers, who were hardest hit before the United States, are now rebounding from the pandemic.

“I really see Europe kind of [on the] leading edge of the recovery side of this,” he said.

In particular, northern Italy struggled with high numbers of confirmed COVID-19 cases, leading Italian defense firm Leonardo, which runs an F-35 final assembly and check out plant in Cameri, to shut down operations over a two day period in March to clean the facility. With the number of new cases receding, Italy began reopening nonessential businesses this month.

“Leonardo today is north of 90 percent manned, fully operating. They're pretty much back to normal operations,” Ulmer said.

The ongoing expulsion of Turkish suppliers from the F-35 program is also unlikely to be affected by the production slowdown at Fort Worth, as Lockheed has already identified companies to take over that work, he said. “With the vast majority of those, that alternate sourcing has been accomplished. I really don't see this as an impact to that."

Ramping production back up

Unless COVID-19 cases spike in the coming months, Lockheed believes it will be able to return workers to a normal production schedule in the late summer or early fall.

What will vary is timing for when suppliers can return to their usual production rates, and whether those suppliers have the capacity to expedite the manufacturing of key parts, Ulmer said. Once the supply chain has fully recovered, it will take the Fort Wort line two to three months to resume full rate production.

“There are 1,900 suppliers across the program” in the United States, Ulmer said. “So we take all that information in, we determine what rate they can deliver to, we determine if they have any kind of constraints we can help them deal with, and then we have to balance that into the production system to dial in the production rate we can execute.”

“I am optimistic that the majority of industry is on the backside. I'm reluctant to say that because there could be a rebound,” Ulmer said, “but we're at the very back end of the impact.”

https://www.defensenews.com/breaking-news/2020/05/19/lockheed-to-slow-f-35-production-as-supply-chain-struggles-to-keep-up

On the same subject

  • Deadlines for B-21 Raider and ARCYBER

    March 3, 2021 | International, C4ISR, Security

    Deadlines for B-21 Raider and ARCYBER

    The B-21 Training Systems Innovation Challenge Deadline: WEDNESDAY 3 March 2021 The U.S. Air Force Global Strike Command and Rapid Capabilities Office have launched an innovation challenge on Vulcan focused on the B-21 Raider Training Systems. The results of the challenge will inform USAF decisions on the adoption of innovative solutions that enhance training systems for pilots and maintainers. The challenge is the continuation of a user-centered innovation effort spurred by a multidisciplinary USAF team (incl. end users) and—depending on merit and viability —provides the opportunity to: Engage with a state-of-the-art program and receive direct operator feedback. Be selected for a funded prototype demonstration Be considered for other potential development and/or integration activities beyond initial demonstration. Don't delay your engagement with this challenge. You can continue editing your submission all the way until the deadline next Wednesday 3 March 2021. Submit your innovations in Vulcan U.S. Army Cyber PAI Tools, Analytics, and Visualization Assessment Event (AE) Deadline: TUESDAY 2 March 2021 The U.S. Army Cyber Command (ARCYBER) Technical Warfare Center (TWC), is in search of industry expertise, software integration, analytic development, and data visualization capabilities to allow real-time, near real-time, and historical analysis of publicly available information (PAI). This call is interested in technologies that provide some or all of the following capabilities: Data Acquisition and Storage Data Structuring, Preparation, and Integration Data Analytics Data Visualization Submit your relevant capabilities to ARCYBER Cyber Fusion Innovation Center (CFIC) HERE by next Tuesday 2 March 2021. Review the instructions and be proactive in your submission process in order to increase the effectiveness of your engagement. IT TAKES A NETWORK!

  • EMSA/OP/1/2021

    April 8, 2021 | International, Aerospace, Naval

    EMSA/OP/1/2021

    Lightweight RPAS Services Supporting Pollution Response and Multipurpose Maritime Surveillance

  • U.S. Navy Commissions Littoral Combat Ship 15 (Billings)

    August 5, 2019 | International, Naval

    U.S. Navy Commissions Littoral Combat Ship 15 (Billings)

    KEY WEST, Fla., Aug. 3, 2019 /PRNewswire/ -- The U.S. Navy commissioned USS Billings (LCS 15) – the nation's eighth Freedom-variant Littoral Combat Ship (LCS) – in Key West, Florida. This milestone places the ship, built by the Lockheed Martin (NYSE: LMT) -led team into active service. "Billings was designed to operate and adapt to a rapidly changing environment," said Joe DePietro, vice president of Small Combatants and Ship Systems at Lockheed Martin. "She is equipped and ready for today's threats and easily modifiable to meet the threats we may not even be aware of yet. Our team is confident Billings will be what the Navy needs when the fleet needs it." Unique among combat ships, LCS is designed to complete close-to-shore missions and is a growing and relevant part of the Navy's fleet. It is fast — capable of speeds in excess of 40 knots. It is automated — with the most efficient staffing of any combat ship. It is lethal — standard equipped with Rolling Airframe Missiles (RAM) and a Mark 110 gun, capable of firing 220 rounds per minute. It is flexible — with 40 percent of the hull easily reconfigurable, integrating capabilities like the Longbow Hellfire Missiles, 30mm guns, and manned and unmanned vehicles targeted to meet today's and tomorrow's missions. "Having now commanded two freedom class LCS variants, I would like to report that these ships are truly impressive and will fit well in the niche they have been designed for," said LCS 15's Commanding Officer, Commander Nathan Rowan. "They are fast, maneuverable, and their weapon systems are some of the most accurate I've witnessed on any platform of which I've previously served." There are seven ships in various stages of production and test at Fincantieri Marinette Marine in Wisconsin, where the Freedom-variant LCS is built. The next Freedom-variant in the class is LCS 17, the future USS Indianapolis, which was delivered in late July. "On behalf of the proud 2,000 men and women who transform flat steel into a fast, agile surface combatant," said Jan Allman, CEO of Fincantieri Marinette Marine, "we are honored to support the U.S. Navy, and we congratulate the outstanding crew of the USS Billings." Multimedia assets are available here: Social media video: https://vimeo.com/351803068 B-roll: https://vimeo.com/351805414 Photos: https://www.flickr.com/photos/143371902@N04/albums/72157710070352016 For more information, visit www.lockheedmartin.com/lcs. https://news.lockheedmartin.com/2019-08-03-U-S-Navy-Commissions-Littoral-Combat-Ship-15-Billings

All news