June 29, 2020 | International, Naval

Here’s why Britain is struggling to form a fully effective carrier strike group

By:

LONDON — Britain's Royal Navy took delivery of two new aircraft carriers, but a government report on the ships achieving operational capability has laid bare some obstacles toward making a fully effective carrier strike group.

In a report released June 25, the National Audit Office pointed to delays in developing the Crowsnest airborne early warning radar and contracting to build the logistics ships destined to support the 65,000-ton carriers as ongoing problems for the Royal Navy. The NAO also raised questions about future funding.

The Ministry of Defence is making slow “progress in developing the crucial supporting activities that are needed to make full use of a carrier strike group, such as the Crowsnest radar system and the ability to resupply the carriers. In addition, it has not established a clear view on the future cost of enhancing, operating and supporting carrier strike, which creates the risk of future affordability pressures,” the NAO said.

Added the head of the watchdog: “The MoD also needs to get a firmer grip on the future costs of carrier strike. By failing to understand their full extent, it risks adding to the financial strain on a defense budget that is already unaffordable.”

HMS Queen Elizabeth, the first of two carriers built by British industry in a £4.6 billion (U.S. $5.7 billion) program, is already undertaking extensive sea trials, with its F-35B jets ahead of a planned first deployment next year.

The second carrier, HMS Prince of Wales, is also conducting sea trials but is some months behind its sister ship. The warships are not expected to be operated simultaneously.

The NAO said the Lockheed Martin-led program to install Crowsnest radars on Royal Navy Merlin helicopters is running 18 months late and will impact how the British carrier strike force is initially deployed. The watchdog said the MoD is working to come up with an acceptable baseline radar by the time HMS Queen Elizabeth undertakes its initial deployment next year.

“As at April 2020, the Department [the MoD] expected to achieve initial Crowsnest operating capability in September 2021, some 18 months later than planned,” the NAO reported. “As this is later than the December 2020 milestone for declaring initial operating capability for carrier strike, the Department is working to provide a credible baseline radar capability for the first deployment with the United States in 2021. It expects to recover some lost time to declare full operating capability in May 2023, 11 months later than planned. However, the existing timetable contains no contingency to accommodate any further slippage. The delays will affect how the Department can use carrier strike during this period.”

British and U.S. Marine Corps jets will be based on the carrier during its first deployment, partly because the U.K. does not have a sufficient inventory of available jets. Eighteen of the aircraft have so far been delivered for use by the Royal Navy and the Royal Air Force

Lockheed Martin secured the Crowsnest contract in 2017, with Searchwater radar supplier Thales and helicopter builder Leonardo as subcontractors.

Crowsnest is a key element in the protection of the naval strike group, giving air, maritime and land detection and tracking capabilities.

The NAO said the delay “has been caused by a subcontractor, Thales, failing to meet its contractual commitments for developing equipment and not providing sufficient information on the project's progress. Neither MoD nor its prime contractor, Lockheed Martin, were aware of these problems until it was too late, reflecting MoD's ineffective oversight of its contract with Lockheed Martin.”

A Lockheed Martin UK spokesperson said the company is working to deliver the Crowsnest capability in time for HMS Queen Elizabeth's deployment.

“As prime contractor for Crowsnest, we understand the fundamental component that this program delivers to the UK's Carrier Enabled Power Projection. We will continue to ensure that the program develops in line with our requirement to deliver the Crowsnest capability to support the first operational deployment of HMS Queen Elizabeth,” the spokesperson said. “We will work with our industrial partners and the MoD to address any developmental issues which arise, including the deployment of additional resources, if necessary, to maintain program timescales and deliver this critical capability to the Royal Navy.”

Thales UK did not respond to Defense News' requests for comment by press time.

The NAO partly blames the setbacks for why the MoD faces a “tight timetable” to develop full operating capability for a strike group by 2023. But the watchdog also highlighted the Fleet Solid Support program as another obstacle.

The MoD had targeted 2026 for when the first of up to three logistics ships could provide ammunition, food and general stores to the carrier strike group, but that timeline has extended by up to three years as a result of ongoing uncertainty over the schedule to compete and build the vessels operated by the Royal Fleet Auxiliary.

The MoD abandoned a competition to build the ships late last year, saying it was concerned about obtaining value for money. At the time, the program was mired in controversy over whether the contract should go to a British shipyard consortium or awarded to a foreign company. That issue remains unresolved.

No date has officially been given for restarting the competition. Defence Secretary Ben Wallace told the parliamentary Defence Committee earlier this year that he thinks it will relaunch in September, but that has not been confirmed.

Defence Committee Chairman Tobia Ellwood was particularly critical of the failure to provide the necessary support ships, noting that without them, the carriers' capability would be seriously undermined.

“It'll be hotched and potched, only available for short operational journeys,” he told the Daily Telegraph on June 26. “It will be for display purposes only, and that's a very expensive toy.”

Britain has only one solid support vessel, RFA Fort Victoria, that can replenish a carrier at sea. It entered service in 1994 and is due to retire in 2028, having had its life expectancy extended.

The NAO report said the limitations of RFA Fort Victoria would have a knock-on effect to carrier operations.

“Having only one support ship with limited cargo capacity slows the tempo and reach at which the Department [the MoD] can replenish a carrier group. In addition, the Department will have restricted options for deploying the carriers for much of 2022 because RFA Fort Victoria will be unavailable due to major planned maintenance work,” the NAO said.

Responding to the report, an MOD spokesperson said: ”Carrier strike is a complex challenge, which relies on a mix of capabilities and platforms. We remain committed to investing in this capability, which demonstrates the U.K.'s global role.

“Despite the disruptions of COVID-19, the carrier strike group is on track for its first operational deployment.”

https://www.defensenews.com/naval/2020/06/26/heres-why-britain-is-struggling-to-form-a-fully-effective-carrier-strike-group/

On the same subject

  • Défense : l’avion de combat européen du futur (SCAF) embourbé dans les rivalités entre industriels et grandes puissances

    March 22, 2021 | International, Aerospace

    Défense : l’avion de combat européen du futur (SCAF) embourbé dans les rivalités entre industriels et grandes puissances

    Capital pour la coopération européenne en matière de défense, le projet de Système de combat aérien futur (SCAF) est fragilisé, alors que les parties prenantes (pays participants et géants de la défense)

  • With demand high in Ukraine, US Army ramps up artillery production

    January 26, 2023 | International, Land

    With demand high in Ukraine, US Army ramps up artillery production

    As Ukraine rapidly burns through 155mm artillery rounds to fight back the Russian invasion, the U.S. Army is scrambling to increase production capacity.

  • Sprint toward new missile-warning satellites begins with first contract award to Lockheed

    August 16, 2018 | International, C4ISR

    Sprint toward new missile-warning satellites begins with first contract award to Lockheed

    By: Valerie Insinna WASHINGTON — The U.S. Air Force is racing to kick-start its new accelerated program to buy next-generation missile warning satellites, awarding a contract on Aug. 14 to Lockheed Martin for the first three satellites in the Next-Generation Overhead Persistent Infrared program. The award, which has a value of up to $2.9 billion, will allow Lockheed to do the design work, flight hardware procurement, early manufacturing and risk-reduction work necessary for a critical design review, the service said in a statement. Lockheed is set to provide the three geosynchronous Earth orbit satellites in the Next-Gen OPIR constellation. "As we develop these new systems, speed matters," Air Force Secretary Heather Wilson said in a statement. "We are focused on providing a missile warning capability survivable in a contested environment by the mid-2020s." More specifically, the Air Force has said it plans to launch its first Next Gen OPIR satellite in 2023, two years earlier than its original plan to begin fielding the replacement for the Space Based Infrared System, or SBIRS, which called for first launches in 2025. Gen. John Hyten, commander of U.S. Strategic Command, was one of the biggest critics of the Air Force's original procurement strategy for a next generation SBIRS. In December, he called the service's plan to field the new constellation by fiscal 2029 “ridiculous” and said it could be done faster. Full article: https://www.defensenews.com/space/2018/08/15/sprint-towards-new-missile-warning-satellites-begins-with-first-contract-award-to-lockheed

All news