January 2, 2019 | International, Aerospace
By: Valerie Insinna
ASHINGTON — Boeing won't be delivering the first KC-46 tanker to the Air Force in 2018 as planned, due to Defense Secretary Jim Mattis' surprise ouster from the Pentagon, a source told Defense News on Monday.
The Air Force had intended to accept the first KC-46 by the end of December and was awaiting signature from Mattis, which would finalize the delivery plans, Reuters first reported on Dec. 20.
However, later that day, Mattis announced that he would step down from the top Defense Department post in February, and just three days later, President Donald Trump tweeted that Mattis would wrap up his work as secretary of defense by the end of 2018.
With sweeping changes in leadership at the Pentagon imminent, a decision on KC-46 was pushed out, a source close to the program told Defense News. The situation was further complicated because Deputy Secretary of Defense Patrick Shanahan — who by the end of Dec. 31 will temporarily take over Mattis' role as defense secretary — is a former Boeing executive and must recuse himself from all decisions involving the company.
Boeing declined to confirm that the delivery would not take place on Dec. 31.
“KC-46 remains a top priority and we look forward to delivering tanker aircraft in partnership with the Air Force,” said Kelly Kaplan, a spokeswoman for the company, in a statement to Defense News.
The Air Force did not immediately respond to a request for comment.
The delay is a blow for Boeing, which had promised to deliver the first tanker by the end of 2018 after a string of missed delivery dates stemming back to August 2017.
“We continue to make steady progress toward final certification of the KC-46 tanker,” Boeing's CEO Dennis Muilenburg said in an October earnings call. “We are working with our U.S. Air Force customer toward completing all the steps required to deliver the first tanker aircraft this quarter."
The company has now racked up more than $3 billion in pre-tax charges on the program, as it is responsible for any costs beyond the $4.9 billion fixed price contract value originally awarded in 2011.
Boeing officials are hopeful that the Air Force will be able to move forward with delivery after a set of meetings in early 2019, one source said.
But at the moment it is unclear who will authorize the KC-46 delivery with Shanahan barred from the process, though it may fall to Air Force Secretary Heather Wilson or to Ellen Lord, undersecretary of defense for acquisition and sustainment.
The Air Force plans to buy 179 KC-46s throughout its program of record. McConnell Air Force Base in Kansas is set to become the first installation to receive the new tankers, and training for pilots and boom operators has already begun.
https://www.defensenews.com/air/2018/12/31/first-kc-46-delivery-stalled-by-mattis-departure
April 16, 2024 | International, Aerospace
The contract, which is worth $320 million, also includes reconnaissance pods and training armaments, such as AIM-9X and AIM-120 missiles.
March 13, 2023 | International, Aerospace
The Danish Defence Ministry has issued a multimillion-dollar tender for several small drones intended for intelligence, surveillance and reconnaissance.
January 24, 2020 | International, Aerospace, Naval, Land, C4ISR, Security
ARMY Brayman Construction Corp., Saxonburg, Pennsylvania, was awarded a $319,592,539 firm-fixed-price contract for labor, rehabilitation of recreational areas, equipment, supervision and modifications to the stilling basin of the Bluestone Dam in Hinton, West Virginia. Bids were solicited via the internet with one received. Work will be performed in Hinton, West Virginia, with an estimated completion date of Jan. 31, 2029. Fiscal 2018 operations and maintenance, civil works funds in the amount of $319,592,539 were obligated at the time of the award. U.S. Army Corps of Engineers, Huntington, West Virginia, is the contracting activity (W91237-20-C-0004). Science Applications International Corp., Reston, Virginia, was awarded a $12,847,708 cost-no-fee and firm-fixed-price contract for information technology support services. Bids were solicited via the internet with six received. Work will be performed in Pyeongtaek, South Korea, with an estimated completion date of Jan. 31, 2025. Fiscal 2020 operations and maintenance, Army funds in the amount of $12,847,708 were obligated at the time of the award. 411th Contracting Support Brigade, Seoul, South Korea, is the contracting activity (W91QVN-20-F-0157). DEFENSE LOGISTICS AGENCY Simulab Corp., Seattle, Washington, has been awarded a maximum $36,000,000 fixed-price with economic-price-adjustment, indefinite-delivery/indefinite-quantity contract for hospital equipment and accessories for the Defense Logistics Agency electronic catalog. This is a five-year contract with no option periods. This was a competitive acquisition with 102 responses received. Location of performance is Washington, with a Jan. 22, 2025, performance completion date. Using military services are Army, Navy, Air Force and Marine Corps. Type of appropriation is fiscal 2020 through 2025 defense working capital funds. The contracting activity is the Defense Logistics Agency Troop Support, Philadelphia, Pennsylvania (SPE2DH-20-D-0029). NAVY PAE Applied Technologies LLC, Arlington, Virginia, is awarded a $32,967,099 modification (P00342) to a previously awarded contract N66604-05-C-1277 to extend the period of performance for six months and increase target cost for Atlantic Undersea Test and Evaluation Center (AUTEC). AUTEC is the Navy's large-area, deep-water, undersea test and evaluation range. Underwater research, testing and evaluation of anti-submarine weapons, sonar tracking and communications are the predominant activities conducted at AUTEC. The contractor performs AUTEC range operations support services and maintenance of facilities and range systems. In addition, the contractor is responsible for operating a self-sufficient one square mile Navy outpost. This modification increases the value of the basic contract by $32,967,099. The new total value is $885,984,261. Work will be performed in Andros Island, Commonwealth of the Bahamas (80%); and West Palm Beach, Florida (20%), and is expected to be completed in September 2020. No funding will be obligated at time of this modification award. The Naval Undersea Warfare Center Newport Division, Newport, Rhode Island, is the contracting activity. https://www.defense.gov/Newsroom/Contracts/Contract/Article/2064381/source/GovDelivery/