14 juin 2018 | International, Aérospatial, C4ISR

House wants better tech at the Air Force’s space ops center

The U.S. House of Representatives issued a rebuke to the Air Force's long-awaited space object tracking system in the annual defense authorization bill, which passed May 24.

An amendment to the fiscal 2019 National Defense Authorization Act restricted all funding to theAir Force's Joint Space Operations Center (JSpOC) Mission System (JMS) until the Pentagon can show Congress that the program's contract embraces “best-in-breed” technology to fill gaps in current space situational capabilities.

The White House objected to the decision from Congress, arguing that excessive oversight will impose a burden on the Air Force, further delaying the already time strained program.

“This provision will add additional cost and schedule to [JMS] and delay delivery of a critical space situational awareness capability to the warfighter,” administration officials said in a statement.

A final version of the bill must pass both chambers of Congress.

The Government Accountability Office released a report May 24 detailing the continued setbacks of the second increment of JSpOC JMS. The report says the program has been delayed by two years and 11 months and attributed the slip to the $18.9 million in funding reductions through fiscal years 2013 and 2014.

The GAO has said the total cost of the second increment of the program is about $320 million.

The JMS will replace the Air Force's Space Defense Operations Center (SPADOC), a system long begrudged by officials as dilapidated and difficult to maintain. Gen. John Hyten, the former head of Air Force Space Command, once described the legacy system as “that ancient engine that can't take data from anywhere unless it's one of ours.”

Despite continued calls for system upgrades, the new system is currently scheduled to be launched in June 2019, almost three years later than its original schedule date of July 2016. In the GAO's analysis of the program, the congressional watchdog was unable to obtain performance data from JMS because the program is still in an “early development” phase.

In September 2016, after missing a key deadline, the Air Force issued to Congress a critical change report regarding the JMS, formally eliminating several of the program's capability goals and delaying its estimated delivery date from July 2016 to May 2019.

The JMS is part of a larger effort from the Air Force to modernize the Joint Space Operations Center, the processing center of U.S. military space operations. The program aims to replace or upgrade the hardware and software currently used for space surveillance, collision avoidance, launch support, and providing more precise and timely orbital information from data gathered the service's object tracking system, known as Space Fence.

https://www.c4isrnet.com/it-networks/2018/05/31/house-wants-better-tech-at-the-air-forces-space-ops-center/

Sur le même sujet

  • After a hard-fought competition, ULA and SpaceX to remain military’s rocket launch providers

    11 août 2020 | International, Aérospatial

    After a hard-fought competition, ULA and SpaceX to remain military’s rocket launch providers

    By: Valerie Insinna WASHINGTON — United Launch Alliance and SpaceX have won the Space Force's next-generation rocket contract, locking the two companies in as the Defense Department's launch providers of choice for the foreseeable future. ULA — a joint venture of Lockheed Martin and Boeing — was awarded $337 million, while SpaceX will be getting $316 million for phase two of the National Security Space Launch (NSSL) program, the Pentagon announced Aug. 7. They beat out Blue Origin and Northrop Grumman. Phase 2 of the NSSL program is the U.S. military's vehicle for ordering launch services from fiscal year 2022 to 2027. ULA is slated to get 60 percent of the manifest, with SpaceX getting the remainder. “We don't think this is the last round of innovation that we're going to see,” Will Roper, the Air Force's acquisition executive, told reporters during an Aug. 7 roundtable. “Although we're excited for the next five years, we're looking ahead to ‘Phase 3' five years from now and wondering what new leap-ahead, lower-cost technologies might be on the forefront to make assured access to space not just assured, but cheaper.” The award pays for the first three missions in 2022, which include two ULA launches and one for SpaceX. All are classified, Roper said. There is no ceiling on the number of launches that the Pentagon can order in Phase 2, but Roper expects about 32 missions. Funding for those missions will be distributed in future task orders. The NSSL Phase 2 award moves the U.S. military one step closer to eliminating its dependence on the Russian RD-180 engine, which is used in ULA's Atlas V rocket. The Defense Department has until 2022 to stop RD-180 procurement, and Roper said he was confident was on “a low risk path” to ensure it will meet that deadline. For the Phase 2 SpaceX offered the Falcon 9 and Falcon Heavy, which are both certified and in use. ULA proposed a new rocket, the Vulcan Centaur, which is under development and expected to make its maiden flight in 2021. “Vulcan Centaur is the right choice for critical national security space missions and was purpose built to meet all of the requirements of our nation's space launch needs,” said Tory Bruno, ULA's president and CEO, said in a statement. Blue Origin and Northrop Grumman were also in the process of creating new launch systems under a 2018 agreement with the Space and Missile Systems Center. That organization will now work with those companies on how to best halt the government's involvement in that development, Roper said. “We will tie off the [launch service agreement] contracts as soon as we can, at a point that makes sense,” he said. “We want to make sure that work that's in flux, that we're able to document what the vendors have done. Where the government has rights to the data and the work, we want to make sure we retain them.” Unless the companies protest the contract award, the next opportunity for Northrop, Blue Origin or other challengers to compete for national security launches is NSSL Phase 3, but the department's approach and timeline for that effort is still being determined. “If funding were available for a Phase 3 launch service agreement, there's no prohibition on how early we could start Phase 3,” said Roper, who added that studies have shown “some strategic benefits for doing that sooner rather than later.” https://www.defensenews.com/space/2020/08/07/after-a-hard-fought-competition-ula-and-spacex-to-remain-militarys-rocket-launch-providers/

  • Submarine maker to add jobs amid $39 billion backlog in work

    2 février 2021 | International, Naval

    Submarine maker to add jobs amid $39 billion backlog in work

    By: The Associated Press GROTON, Conn. — General Dynamics Electric Boat plans to add 2,200 jobs this year in Connecticut and Rhode Island as it tackles a $39 billion backlog of work, the submarine maker's top executive said Monday. Kevin Graney, Electric Boat's president, made the announcement during a video briefing for stakeholders. He said the company is facing the largest backlog of work in its history, with orders to build two new ballistic missile submarines and 19 new attack submarines, 11 of which are currently under construction. The company added more than 2,000 jobs a year ago, much of it at the company's Quonset Point site in Rhode Island. The new jobs will include shipyard workers, engineers and support staff, Graney said, and the firm expects to be in a “stable hiring mode pretty much for the next decade.” “We're going to need to sustain the Rhode Island workforce as we grow the Connecticut workforce,” he said. Electric Boat employs more than 17,000 people, including about 12,000 at its Groton shipyard and more than 4,000 in Rhode Island. Congress increased funding for submarine programs from about $11.1 billion during the last fiscal year to $11.6 billion this fiscal year. Members of Connecticut's all-Democrat congressional delegation, who took part in the video conference, said the defense contractor can expect to continue receiving work under the Biden administration. “It may be unmanned as well as manned weapons platforms, but the future of the submarine is critically important,” U.S. Sen. Richard Blumenthal said. https://www.defensenews.com/industry/2021/02/01/submarine-maker-to-add-jobs-amid-39-billion-backlog-in-work/

  • Amid high hopes, can the European Patrol Corvette deliver?

    4 novembre 2021 | International, Naval

    Amid high hopes, can the European Patrol Corvette deliver?

    An industrial source told Defense News that each vessel is expected to cost around '‚¬250-300 million, making the Corvette program worth '‚¬5-6 billion, even before Greece confirms an order and any new members sign up.

Toutes les nouvelles