3 octobre 2024 | International, C4ISR, Sécurité

HII is Awarded a $458 Million Contract to Modernize IT Architecture for U.S. Department of Defense

The enhancements will provide end users, including U.S. Department of Defense service components and the U.S. Special Operations Command, with IT services and solutions to support the warfighters.

https://www.epicos.com/article/875026/hii-awarded-458-million-contract-modernize-it-architecture-us-department-defense

Sur le même sujet

  • Lockheed deems first test shot of precision strike missile a success, amid Raytheon delay

    11 décembre 2019 | International, Terrestre

    Lockheed deems first test shot of precision strike missile a success, amid Raytheon delay

    By: Jen Judson WASHINGTON — The first test shot of Lockheed Martin's precision strike missile at White Sands Missile Range, New Mexico, was a success, the company said in a statement. “All test objectives were achieved,” the statement read. The PrSM was fired Dec. 10 from a U.S. Army High Mobility Artillery Rocket System launcher and flew roughly 240 kilometers to the target, the release stated. “Today's success validates all of the hard work our PrSM team has put into the design and development of this missile,” said Gaylia Campbell, the company's vice president of precision fires and combat maneuver systems. “This test flight is the most recent success in a long line of product component and sub-component testing successes conducted as part of our proven development discipline to assure total mission success for our U.S. Army customer.” The test objectives, according to Lockheed, included staying on course and maintaining the trajectory, range and accuracy. The first flight tests for PrSM — meant to replace the Army Tactical Missile System — were delayed until the end of this year due to technical issues, the director in charge of Long-Range Precision Fires modernization, Brig. Gen. John Rafferty, said in July. “There were a couple of technical issues that caused us to delay about 90 days for the flight test," he said. "There was a mishap at a facility that caused some of the delay, followed by Mother Nature ... extreme weather that made repair at that facility near impossible for a period of time.” When pressed for specifics, Rafferty said the mishap was not at a Raytheon or Lockheed facility, but rather a sub-vendor used by both teams. Raytheon and Lockheed Martin have been in a head-to-head competition to deliver a future PrSM missile to the Army. While Lockheed was originally intended to test its missile in flight after Raytheon, the latter defense company experienced technical issues, according to sources, and had to push its flight test from November to early next year. The Army has a goal to initially field a new PrSM in 2023; it is one of the major development efforts within the Army's long-range precision fires portfolio. LRPF is the Army's top modernization priority. The service has accelerated PrSM's fielding timeline by several years and will stick to the baseline requirements for the missile to get there. Each company will have subsequent flight tests after the initial shot to help garner further data for development and refinement, leading the Army to choose a winner. The Army also plans to adjust its maximum range requirement following critical test shots of the two PrSMs. The missile's current maximum range requirement is 499 kilometers, which is the range that was compliant under the now-collapsed Intermediate-Range Nuclear Forces Treaty between the United States and Russia. The United States withdrew from the treaty in August, and so the Army no longer has to adhere to the range limit for its missiles. Rafferty said the baseline missile could reach a range of 550 kilometers based on data from both companies competing to build the PrSM. But the Army won't consider adjusting its requirements until each company has observed how their respective missile behaves in real flight tests. https://www.defensenews.com/land/2019/12/10/lockheed-deems-first-test-shot-of-the-precision-strike-missile-a-success-raytheons-is-delayed

  • Estonian military robot maker weighs production in Ukraine

    11 janvier 2024 | International, C4ISR

    Estonian military robot maker weighs production in Ukraine

    The yard is a “few hundred” workers short, Andy Bosak, the deputy program manager, said at the Surface Navy Association’s annual conference.

  • Here’s why Britain is struggling to form a fully effective carrier strike group

    29 juin 2020 | International, Naval

    Here’s why Britain is struggling to form a fully effective carrier strike group

    By: Andrew Chuter LONDON — Britain's Royal Navy took delivery of two new aircraft carriers, but a government report on the ships achieving operational capability has laid bare some obstacles toward making a fully effective carrier strike group. In a report released June 25, the National Audit Office pointed to delays in developing the Crowsnest airborne early warning radar and contracting to build the logistics ships destined to support the 65,000-ton carriers as ongoing problems for the Royal Navy. The NAO also raised questions about future funding. The Ministry of Defence is making slow “progress in developing the crucial supporting activities that are needed to make full use of a carrier strike group, such as the Crowsnest radar system and the ability to resupply the carriers. In addition, it has not established a clear view on the future cost of enhancing, operating and supporting carrier strike, which creates the risk of future affordability pressures,” the NAO said. Added the head of the watchdog: “The MoD also needs to get a firmer grip on the future costs of carrier strike. By failing to understand their full extent, it risks adding to the financial strain on a defense budget that is already unaffordable.” HMS Queen Elizabeth, the first of two carriers built by British industry in a £4.6 billion (U.S. $5.7 billion) program, is already undertaking extensive sea trials, with its F-35B jets ahead of a planned first deployment next year. The second carrier, HMS Prince of Wales, is also conducting sea trials but is some months behind its sister ship. The warships are not expected to be operated simultaneously. The NAO said the Lockheed Martin-led program to install Crowsnest radars on Royal Navy Merlin helicopters is running 18 months late and will impact how the British carrier strike force is initially deployed. The watchdog said the MoD is working to come up with an acceptable baseline radar by the time HMS Queen Elizabeth undertakes its initial deployment next year. “As at April 2020, the Department [the MoD] expected to achieve initial Crowsnest operating capability in September 2021, some 18 months later than planned,” the NAO reported. “As this is later than the December 2020 milestone for declaring initial operating capability for carrier strike, the Department is working to provide a credible baseline radar capability for the first deployment with the United States in 2021. It expects to recover some lost time to declare full operating capability in May 2023, 11 months later than planned. However, the existing timetable contains no contingency to accommodate any further slippage. The delays will affect how the Department can use carrier strike during this period.” British and U.S. Marine Corps jets will be based on the carrier during its first deployment, partly because the U.K. does not have a sufficient inventory of available jets. Eighteen of the aircraft have so far been delivered for use by the Royal Navy and the Royal Air Force Lockheed Martin secured the Crowsnest contract in 2017, with Searchwater radar supplier Thales and helicopter builder Leonardo as subcontractors. Crowsnest is a key element in the protection of the naval strike group, giving air, maritime and land detection and tracking capabilities. The NAO said the delay “has been caused by a subcontractor, Thales, failing to meet its contractual commitments for developing equipment and not providing sufficient information on the project's progress. Neither MoD nor its prime contractor, Lockheed Martin, were aware of these problems until it was too late, reflecting MoD's ineffective oversight of its contract with Lockheed Martin.” A Lockheed Martin UK spokesperson said the company is working to deliver the Crowsnest capability in time for HMS Queen Elizabeth's deployment. “As prime contractor for Crowsnest, we understand the fundamental component that this program delivers to the UK's Carrier Enabled Power Projection. We will continue to ensure that the program develops in line with our requirement to deliver the Crowsnest capability to support the first operational deployment of HMS Queen Elizabeth,” the spokesperson said. “We will work with our industrial partners and the MoD to address any developmental issues which arise, including the deployment of additional resources, if necessary, to maintain program timescales and deliver this critical capability to the Royal Navy.” Thales UK did not respond to Defense News' requests for comment by press time. The NAO partly blames the setbacks for why the MoD faces a “tight timetable” to develop full operating capability for a strike group by 2023. But the watchdog also highlighted the Fleet Solid Support program as another obstacle. The MoD had targeted 2026 for when the first of up to three logistics ships could provide ammunition, food and general stores to the carrier strike group, but that timeline has extended by up to three years as a result of ongoing uncertainty over the schedule to compete and build the vessels operated by the Royal Fleet Auxiliary. The MoD abandoned a competition to build the ships late last year, saying it was concerned about obtaining value for money. At the time, the program was mired in controversy over whether the contract should go to a British shipyard consortium or awarded to a foreign company. That issue remains unresolved. No date has officially been given for restarting the competition. Defence Secretary Ben Wallace told the parliamentary Defence Committee earlier this year that he thinks it will relaunch in September, but that has not been confirmed. Defence Committee Chairman Tobia Ellwood was particularly critical of the failure to provide the necessary support ships, noting that without them, the carriers' capability would be seriously undermined. “It'll be hotched and potched, only available for short operational journeys,” he told the Daily Telegraph on June 26. “It will be for display purposes only, and that's a very expensive toy.” Britain has only one solid support vessel, RFA Fort Victoria, that can replenish a carrier at sea. It entered service in 1994 and is due to retire in 2028, having had its life expectancy extended. The NAO report said the limitations of RFA Fort Victoria would have a knock-on effect to carrier operations. “Having only one support ship with limited cargo capacity slows the tempo and reach at which the Department [the MoD] can replenish a carrier group. In addition, the Department will have restricted options for deploying the carriers for much of 2022 because RFA Fort Victoria will be unavailable due to major planned maintenance work,” the NAO said. Responding to the report, an MOD spokesperson said: ”Carrier strike is a complex challenge, which relies on a mix of capabilities and platforms. We remain committed to investing in this capability, which demonstrates the U.K.'s global role. “Despite the disruptions of COVID-19, the carrier strike group is on track for its first operational deployment.” https://www.defensenews.com/naval/2020/06/26/heres-why-britain-is-struggling-to-form-a-fully-effective-carrier-strike-group/

Toutes les nouvelles