24 novembre 2021 | International, Aérospatial, Naval, Terrestre, C4ISR, Sécurité

''No company is immune''€™: Supply chain woes weigh on defense firms

Supply chain problems have hit all sides of the defense industry in unexpected ways -- and small businesses with narrower profit margins are particularly worried about how they can weather this storm.

https://www.defensenews.com/air/2021/11/23/no-company-is-immune-supply-chain-woes-weigh-on-defense-firms

Sur le même sujet

  • The next few months are ‘critical’ for the Army’s new helicopter engine

    11 juin 2020 | International, Terrestre

    The next few months are ‘critical’ for the Army’s new helicopter engine

    By: Aaron Mehta WASHINGTON — The Army's Improved Turbine Engine Program is facing a “critical” stretch which will determine whether testing on the engine will occur on time or be delayed, thanks to challenges related to the COVID-19 pandemic, a pair of Army officials said Wednesday. Patrick Mason, the program executive officer for Army aviation, and Brig. Gen. Walter Rugen, the director for future vertical lift inside Army Futures Command, said that the service has finished its component critical design review (CDR) process, and has moved on to its full program CDR, a key milestone before moving into testing. However, “given COVID and all of the factors that have gone on with COVID,” the plan to have the full CDR done during second quarter has been pushed to third quarter, Mason said at an event hosted by the Heritage Foundation. ITEP is “the number one watch item we've had across the future vertical lift portfolio for COVID impacts,” Mason said, because “hardware needs to be coming in the latter part of this year so we can test at the component level, assemble into the engine, and then go to first engine test.” “So that's going to be critical over the next month to two months, to see where we stand on hardware deliveries with that, and then whether or not we will reach first engine test at the time that we had originally stated,” he said, noting the plan is for engine tests to proceed in 2021. Mason also noted that the delay is less dramatic than it may seem, because the original plan for ITEP called for the full CDR to be completed in the fourth quarter of this year; the Army felt it was ahead of schedule enough to shift that target to second quarter, until COVID caused the delay. In other words, CDR being completed in Q3 still means the program is ahead of its original baseline. General Electric Aviation won the $517 million award for the engineering, manufacturing and development phase in February 2019. The requirements included developing a 3,000 shaft horsepower engine that reduces fuel consumption by 25 percent and increases service life by 20 percent compared to the legacy T700 currently used in the Army's AH-64 Apache and UH-60 Black Hawk helicopters. In addition to replacing the engines on those two leacy platforms, ITEP is expected to power the Future Attack Reconnaissance Aircraft, or FARA design. For the heavier future rotorcraft known as the Future Long-Range Assault Aircraft, or FLRAA, the Army is looking at a heavier engine design, although the companies competing for the design will have the ability to pick their own engine designs as part of their pitches. “We really think the efficiencies there with a two engines strategy across all of Army aviation's tactical fleet would be a powerful way to go at both readiness and affordability concerns,” said Rugen. https://www.defensenews.com/land/2020/06/10/the-next-few-months-are-critical-for-the-armys-new-helicopter-engine/

  • KMW, Nexter and Rheinmetall get the go-ahead for initial MGCS architecture study

    22 mai 2020 | International, Terrestre

    KMW, Nexter and Rheinmetall get the go-ahead for initial MGCS architecture study

    May 20, 2020 - Standing for Main Ground Combat System, MGCS is a joint Franco-German defence project. The programme, to be implemented under German political leadership, is tasked with developing a main combat system to succeed the Bundeswehr's Leopard 2 and the French Army's Leclerc starting in 2035. Making the start of the MGCS procurement programme Krauss-Maffei Wegmann (KMW), Nexter Systems and Rheinmetall AG established an ARGE in December 2019. Now, the partners and the German Federal Office of Bundeswehr Equipment, Information Technology and In-Service Support (BAAINBw), acting in the name of Germany and France, have signed a contract for the “System Architecture Definition Study - Part 1” (SADS Part 1). This contract sounds the industrial starting gun for a MGCS Demonstration Phase At the Franco-German Ministerial Council meeting in Toulouse on 16 October 2019, the defence ministers of both nations, Florence Parly and Annegret Kramp-Karrenbauer, emphasized their commitment to developing the MGCS. The ARGE is a German acronym standing for Arbeitsgemeinschaft, or “working group”. Under German law, the ARGE serves as the contractual partner of the procurement authority (BAAINBw) during the first phase of the programme. Officials of the three companies represent the ARGE vis-à-vis third parties. The aim of the study is to harmonize the final MGCS concepts of the previous phase, to analyse further details, and to propose a common multi-platform architecture. The three contractual partners will assess various aspects of different concepts: technical feasibility in the projected timeframe allotted for the programme; ability to fulfil the operational needs of both armies; efficiency and compatibility with national “systems of systems” (SCORPION for France and Digitization of Land-Based Operations (D-LBO) for Germany). Workshares in the SADS Part 1 are to be distributed equally between France and Germany on a fifty-fifty basis. The first phase of architecture work is expected to last 18 months. View source version on Rheinmetall : https://www.rheinmetall-defence.com/en/rheinmetall_defence/public_relations/news/latest_news/index_23936.php

  • Marshall to produce further torpedo tubes to support major naval vessel programmes

    31 juillet 2024 | International, Terrestre

    Marshall to produce further torpedo tubes to support major naval vessel programmes

    Production will run from 2024 to 2026, with Marshall contracted to manufacture and deliver composite torpedo launcher tubes and associated equipment for integration into SEA’s Torpedo Launcher Systems.

Toutes les nouvelles