January 8, 2024 | International, C4ISR
USS Laboon shoots down Red Sea air drone in ‘self-defense’
The incident comes after the Laboon and F/A-18 Super Hornets shot down more than a dozen drones and missiles last month.
August 4, 2020 | International, Land
By: Jen Judson
WASHINGTON — The coronavirus pandemic has caused another delay for the U.S. Army's plagued M113 replacement program, which has struggled with manufacturing problems as the BAE Systems-made Armored Multi-Purpose Vehicle entered low-rate initial production, according to the company's second quarter fiscal 2020 earnings briefing released last week.
The company had to delay delivery of the first LRIP vehicles by roughly four to six months, moving delivery from March to July.
But as BAE prepared to move ahead on delivery, the pandemic hit, bringing with it another delay of roughly a month, which pushed the vehicles' delivery date to August.
The AMPV program entered LRIP in January 2019, but the program office indicated last year that delivery of the first vehicles would be delayed by two months and the completion of production qualification testing would be delayed by seven months due to tooling and assembly line challenges at BAE's facility in York, Pennsylvania.
Because of the issues, the Army's AMPV budget request in FY21 showed the program took a hit. The service indicated it would buy 32 vehicles instead of the 143 planned for the fiscal year, and the program's budget was cut from $445 million to $193 million.
The Army and BAE developed “a production approach that would allow us to incorporate efficiencies during LRIP that modernize manufacturing and increase the overall throughput of the program,” Amanda Niswonger, a BAE spokeswoman, told Defense News in an Aug. 3 statement.
“This included installing new technology and processes such as robotic welding, digital X-ray, and advanced machining. And we worked closely with the Army to update and refine manufacturing processes to incorporate the most modern weld and inspection technology,” she said. “These changes had an impact on our delivery timeline which was not reflected in the original delivery schedule, but continues to meet the Army's fielding schedule.”
The service and BAE had formalized the schedule change just as COVID-19 hit the U.S., which affected a large number of manufacturing facilities and supply chains globally.
“We have worked tirelessly to mitigate the impacts from COVID-19 with our employees, supply network, and customer base to keep our manufacturing sites operational and continue to receive parts as needed,” Niswonger said. “Unfortunately we could not overcome all the challenges and our first delivery has slipped one month.”
January 8, 2024 | International, C4ISR
The incident comes after the Laboon and F/A-18 Super Hornets shot down more than a dozen drones and missiles last month.
February 3, 2022 | International, C4ISR
Nasittuq Corporation, an Inuit majority-owned corporation, has been awarded a Government of Canada contract to operate and maintain the North Warning System (NWS). The NWS is a joint U.S.-Canadian air defence early warning radar system for North America, managed by the North American Aerospace De
June 10, 2020 | International, Aerospace
By: Valerie Insinna WASHINGTON — The U.S. Air Force will delay a full-rate production milestone for the KC-46 aerial refueling tanker to the end of fiscal 2024 to correspond with a fix for one of the aircraft's key systems, the service announced late Monday. The Pentagon's independent weapons tester — Director of Operational Test and Evaluation Robert Behler — intends to conclude operational testing of the KC-46 only after prime contractor Boeing fixes the tanker's critical deficiencies and has finalized its production configuration. “Accordingly, the Air Force will defer the KC-46 full rate production decision until after the completion of [initial operational test and evaluation], and the receipt of the statutorily-required Beyond Low Rate Initial Production report from [Behler],” the Air Force said in a statement. The KC-46 program has several remaining category 1 deficiencies, the term used by the Pentagon to describe the most serious form of technical problems. Two of the deficiencies involve the aircraft's remote vision system, which is a series of cameras and sensors used by the boom operator to see outside the KC-46 and refuel other aircraft. The Air Force has contended that the RVS does not properly function in all weather and lighting conditions; the service has refused to deploy the KC-46 until the problem is fixed. Boeing in April agreed to completely redesign the system on its own dime, which will take until at least 2023. One other issue involves the KC-46 boom, which was developed to meet NATO-specific requirements but cannot refuel the A-10 aircraft. The Air Force is paying to redesign the boom actuator, as the service signed off on the original design and did not realize until afterward that it did not meet the specifications needed to refuel the A-10. In March, the Air Force announced an additional category 1 deficiency after maintainers found fuel leaking between the tanker's primary and secondary fuel protection barriers. It is unclear whether this is still a problem, as Boeing had already developed a fix and began retrofitting aircraft when the issue was revealed. “Given its confidence in deficiency resolution timelines for both the aerial refueling boom and Remote Vision System, the Air Force is rescheduling the KC-46's Full Rate Production Decision milestone to late Fiscal Year 2024,” the service stated. The Air Force notes that delaying the full-rate production decision will not affect the program's cost — which is locked into place courtesy of a firm, fixed-price deal with Boeing that holds the contractor financially responsible for cost overruns;nor will it cause the service to alter its current delivery schedule. Boeing is already producing KC-46s at “full rate,” which for the program is 15 tankers per year. It delivered the first KC-46 to McConnell Air Force Base, Kansas, in January 2019. Since then, Altus Air Force Base, Oklahoma, and Pease Air National Guard Base, New Hampshire, have also taken on new KC-46s. Boeing is set to produce 179 KC-46s over the program of record. The company has racked up cost overruns of about $4.6 billion in excess of the $4.9 billion contract it was awarded in 2011. https://www.defensenews.com/air/2020/06/09/the-air-force-delays-a-full-rate-production-decision-for-the-kc-46/